A federal judge on Tuesday upheld
the Bush administration's interpretation of dam-relicensing rules
in the 2005 Energy Policy Act, although critics had argued it
could lead to lesser protections for the environment.
U.S. District Judge Marsha Pechman
said the administration did not exceed its authority when it
established procedures for letting dam operators challenge
environmental requirements, such as installing fish ladders and
monitoring water quality.
The Federal Energy Regulatory
Commission issues licenses to operate dams, and often those 30- or
50-year licenses incorporate conditions set by other federal
agencies to protect wildlife.
The Energy Policy Act lets dam
operators challenge such conditions in a hearing before an
administrative law judge. It also allows them to suggest
alternative environmental measures, and requires the judge to
approve those measures if they are "adequate" and will
be less expensive or allow for greater electricity production.
A coalition of environmental and
recreational groups, led by Washington, D.C.-based American
Rivers, did not challenge the law itself. Instead, the coalition
challenged the Bush administration's decision to apply it to dam
relicensing applications that were already under way when the law
took effect. The opponents also said the administration did not
conduct a proper public notice period before implementing the law.
Pechman rejected those arguments.
She said Congress didn't indicate whether it wanted the law
applied to pending applications, and that it was within the
administration's authority to apply it to them. Furthermore, she
said, no public notice period was required.
Dave Kvamme, a spokesman for
Portland, Ore.-based PacifiCorp, welcomed the ruling. He said dam
operators previously had no avenue for challenging environmental
requirements that could cost ratepayers millions of dollars.
"All this does is allow a
licensee to find lower-cost ways of complying with federal
prescriptions that can benefit fisheries, and we believe that's a
good thing," he said.
In August, pursuant to its new
rights under the Energy Policy Act, PacifiCorp appealed a federal
requirement that it build expensive fish ladders on its Klamath
River dams. It lost: An administrative law judge ruled last week
that the company's alternative proposal — capturing the fish and
trucking them around the dams — wasn't good enough. The company
plans to keep pursuing the alternative.
Jan Hasselman, the Earthjustice
lawyer who handled the challenge, said a big concern is that the
Forest Service, the National Marine Fisheries Service and other
agencies that propose the conditions might not have the resources
to conduct hearings and review alternative proposals for all dam
operators that request them. That would leave dam operators in a
good position to negotiate for weaker requirements, he said.
That happened at the West Fork dam
on Boulder Creek in Utah, environmental groups say. The Forest
Service set a minimum water flow as a condition of relicensing the
dam, but when the Garkane Energy Cooperative requested a hearing,
the parties entered settlement talks, and the agency agreed to
lesser flow requirements.
Hasselman said he did not know if
the groups would appeal the ruling.