FERC DAM MEETING:
Confusion reigned at last week’s
Federal Energy Regulatory Commission (FERC)
meeting on the Klamath River
dams as the Commission tried to figure out
how it fit with the Agreement In Principle (AIP)
signed by PacifiCorp, The Dept. of Interior
and the States of California and
Oregon. The
AIP establishes a set of conditions under
which the U.S. Secretary of Interior would
do the necessary studies and cost/benefit
analysis to decide whether four dams are to
be removed on the
Klamath River.
Dr.
John Mudre gave a presentation on six
actions that the Commission is authorized to
take under the Federal Power Act. (1) It can
issue a license to operate the hydropower
facilities. (FERC has already done the
necessary work to issue the license, has
established the conditions for relicensing
and now awaits a clean Water Act
certification from the two States to
finalize. It is presumed that getting this
will be difficult.) (2) It can deny the
license and refer to license surrender
proceedings. (3) After studies are done,
surrender proceedings may result in dam
removal. (4) It can transfer a license. (5)
it can issue a non-power license for just a
dam. (6) It can proceed with a federal take
over of the facility.
Mudre also explained that FERC established a
policy in 2006 regarding “Settlement
Agreements” by interested parties. These are
contractual agreements worked out by
affected parties rather than going to court.
FERC favors such agreements, but does not
automatically accept them and must make a
determination that they are in the public
interest. They also must be focused on
provisions within the jurisdiction and
authority of the FERC and enforceable by the
Commission. FERC should be involved in the
development of such agreements and they must
be brought before the Commission for
approval.
It
was determined that the only provisions
being worked on that would qualify as a
“Settlement Agreement,” under FERC were
interim measures to be taken to protect
endangered coho and sucker fish while the
AIP was in progress. The
vast bulk of the KBRA (Klamath Basin
Restoration Agreement) is entirely outside
the jurisdiction of FERC and
Siskiyou
County remains opposed to this
agreement. I raised the issue, then, whether
the secretive meetings of selected interests
required to sign confidentiality and good
faith agreements favoring dam removal were
allowable under FACA – Federal Advisory
Committee Act, since these weren’t
settlement agreements under FERC. The DOI
Representative indicated he would get back
to me on that.
It
became very clear that the whole
relicensing/dam decommissioning issue is
being removed from the normal FERC process
and, through anticipated Congressional
Legislation, will become an administrative
decision under the Secretary of the
Interior. After significant study, should he
decide that the benefits of dam relicensing
outweigh the costs, then the FERC process
will go back to the point where it is
presently, with a legislative waiver of
Clean Water Act certification. If he decides
that the costs outweigh the benefits, then
ownership of the dams will be transferred to
a third party and they will be removed by
2020-2025.
Because the process has moved out from under
FERC, the protections in that act for public
input are no longer in place. The current
AIP is essentially a
negotiation between PacifiCorp and the
Federal and State governments to establish a
framework on how to proceed along this new
(to be legislated) Administrative path. Our
input is to ensure that various impacts to
Siskiyou
County are properly mitigated, health
and safety concerns are fully addressed, and
that the science is sound. In response to my
concerns expressed at the meeting that a
public process be preserved, I received
assurances from the Dept. of Interior
representative that the decision making
process would be subject to NEPA – the
National Environmental Policy Act.