A
"good effort" to clarify policy issues and narrow areas of
scientific disagreement is ongoing, but federal agencies can't
promise that all will be happy at the end of the long-running
collaboration with
Columbia
River basin
tribes and states on the intricacies of a new hydrosystem salmon
protection plan.
"Some
sovereigns involved in the collaboration have expressed
dissatisfaction with the Federal Defendants' view that the proposed
action and biological opinion are ultimately the work products of
the responsible Federal Agencies," according to the fifth
quarterly status report issued over the course of a court-ordered
remand process that began early last year.
"These
entities have suggested that everything in the remand, including the
drafting of the BA and BiOp, must be done collectively and reflect a
consensus. The Federal Defendants do not believe that this is what
the Court's remand order contemplates, nor is it called for by the
ESA or its implementing regulations," according to the report
filed Feb. 2 with the court by the U.S. Justice Department.
The
collaboration continues via an "iterative process"
involving the "sharing of initial drafts and pieces of drafts
to get input and refine the product," according to the report
filed for NOAA Fisheries, the U.S. Army Corps of Engineers, the U.S.
Bureau of Reclamation and the Bonneville Power Administration.
That
helps to clarify and narrow areas of disagreement, but, "unlike
earlier remand status reports, the current report does not strive to
achieve consensus," the report says.
Instead
sovereign collaborators were invited to summarize their concerns for
the court.
U.S.
District Court Judge James A. Redden in May 2005 declared the NOAA
Fisheries Service's 2004 biological opinion on the Federal Columbia
River Power System contrary to Endangered Species Act requirements.
He
ordered federal agencies in October 2005 to correct the BiOp's legal
deficiencies, working in collaboration with states and tribes.
ESA
BiOps judge whether a planned federal action -- such as hydrosystem
operations -- jeopardizes the survival of listed species, in this
case 12 salmon and steelhead stocks.
Recent
Columbia/Snake hydro system BiOps have included measures to improve
survival within the system as well as off-site actions such as
habitat improvements.
The
mitigation measures have either been encased in the proposed action
or in a "reasonable and prudent alternative" (RPA) to the
action that is spelled out in the BiOp.
The
report says that the proposed action/RPA will be completed by
mid-March by the federal "action" agencies, as will an
accompanying biological assessment. The action agencies include the
U.S. Army Corps of Engineers and Bureau of Reclamation, which
operate federal dams, and the Bonneville Power Administration, which
markets power generated in the federal hydrosystem.
Even
then the documents will be "subject to adjustment based on PWG
discussion before being delivered to NOAA Fisheries." The
remand's Policy Working Group includes representatives of states,
tribes and the federal agencies.
Under
the schedule approved by the court, a final NOAA Fisheries BiOp is
due by July 31.
"Given
the long and often acrimonious debate that has occurred over many of
these issues, the fact that skepticism exists in the Lower Tribes
and, perhaps others, at this juncture is not surprising. However,
the issues of concern will continue to be discussed and
debated," the report says.
The
Nez Perce, Umatilla, Warm Springs and Yakama tribes, in comments
attached to the report, said they have "grave concerns"
that the initial products do not capture remand discussions.
"The
tribes are very concerned that much of the effort put into the
process by non-agency collaborators has been given little
recognition in the current Action Agency product," according to
the tribal comments. "While this may be rectified in future
drafts, the current posture is highly troubling."
"Tribal
concerns, while not specifically limited by this listing, fall
within general categories such as: clear and enforceable methods for
closing survival gaps, clear and enforceable methods for reversing
the trend toward extinction, monitoring any progress in either
regard, mechanisms for curing methods that simply don't perform as
advertised, recognition of hatchery contributions to recovery and
the failure to provide a clear designation of the jeopardy standard
against which to measure any Proposed Action," the tribes say.
The
tribes said they will "continue to work in the collaboration
process in hopes that changes may occur in future products, while
maintaining a healthy degree of skepticism as to potential
outcomes."
The
Spokane Tribe says that the federal agencies participation in the
process has "undergone a perceptible shift" since summer,
developing documents on their own and sharing those products for
discussion and comment.
The
Spokane Tribe also said that those draft documents "do not
reflect key information derived from and work products of the
collaboration." Likewise the Spokane Tribe comments said they
will continue to work in the process.
The
judge has scheduled a 9:30 a.m. status conference on March 9 in
Portland
to discuss the report and process. Comments on the status report
will be accepted through Feb. 16.
A
second status conference will be held that day, at 1:30 p.m., to
check progress on a separate but related remand -- that of a 2004
NOAA BiOp for Bureau irrigation projects in the upper
Snake
River basin
. Like the FCRPS BiOp, it declared the Bureau's planned action did
not jeopardize the survival of listed salmon and steelhead.
Redden
in May of last year declared the upper Snake BiOp invalid as well,
faulting it like the FCRPS BiOp for not doing a
"comprehensive" jeopardy analysis that included the
effects of the proposed action and the existing environmental
baseline.
The
environmental baseline for each BiOp must include the effects of the
other federal action, he said. The judge in September remanded the
upper Snake BiOp and said a new, legal BiOp should be completed
within four months of completion of the FCRPS BiOp.
A
status report also filed Feb. 2 with the court said the Bureau and
NOAA are working to assess the aggregate effects from the two sets
of dam operations.
"These
consultations are both being conducted in accordance with the same
general standards articulated by the Court (to aggregate effects and
comprehensively evaluate the effects of Reclamation's upper Snake
projects with those of the FCRPS, effects in the environmental
baseline and cumulative effects)," the report says.
The
process will use the same jeopardy analytical framework and process
for conducting the comprehensive evaluation that is being developed
FCRPS remand.
"The
methods that NOAA Fisheries has described in memorandums from Bob
Lohn for the FCRPS remand will apply to the upper Snake
Remand," according to the Upper Snake report.
The
Bureau "has spent the past few months identifying the level of
work, types of analyses, technical expertise, and funding required
to complete" a supplement to its November 2004 biological
assessment.
"Staff
and funds have been assigned to conduct the needed analyses and work
has begun," according to the Bureau report. "Reclamation
has actively coordinated with NOAA Fisheries and internally with
staff engaged in the FCRPS remand to ensure that the scope and
scheduled completion of these tasks and that all information
developed is consistent with the framework and metrics being
developed in the FCRPS remand.
"Specifically,
Reclamation scientists are examining existing data on salmon and
steelhead migration, flows, temperatures, and survival;
Reclamation's hydrologists are working on new/additional analyses
and information that will be presented in the supplement; and
completion of the supplement will be coordinated with the
development of the FCRPS Biological Assessment.
"Reclamation
and NOAA Fisheries are actively considering biological, water
quality, and hydrologic data and discussing the potential to adapt
flow augmentation releases to best benefit migrating salmon and
steelhead," the report says.
"All
of the information available in the remand on Reclamation's upper
Snake River projects will be provided to the FCRPS remand in order
to fully evaluate the information in the FCRPS analysis to ensure a
comprehensive analysis," according to the upper Snake remand
status report.
For
information and documents related to FCRPS BiOp litigation go to www.salmonrecovery.gov