
Latest
Ninth Circuit Decision Interpreting Rapanos Extends Clean Water
Act Jurisdiction to Intermittent Streams
By Aaron Courtney, Marten Law Group
October 10,
2007
In the context of affirming a criminal conviction,
the Ninth Circuit has held that a seasonally intermittent stream—dry
for 10 months out of the year, but which ultimately empties into a
river—constitutes a “water of the United States,” and therefore
that adding gravel and other material to the stream—even when it is
dry—falls within federal Clean Water Act (“CWA”) jurisdiction. In U.S.
v. Moses,[1] the Court affirmed the conviction of an
Idaho
man who
deposited materials into the intermittent stream during the 10-month dry
season without a permit. Such activity, the Court held, amounted to the
“discharge of pollutants” prohibited by the CWA despite the absence
of flowing water during the discharge events.[2]
The case illustrates the Ninth Circuit’s
willingness to apply the CWA’s dredge and fill provisions to
intermittent streams, and serves as a sobering reminder of the
significant penalties that can be assessed under the CWA against
property owners, developers, contractors, or others who engage in
earth-moving moving activities within such water features. However, the
Ninth Circuit did not take the opportunity presented by Moses
to discuss in a comprehensive manner how the Court applies
the United States Supreme Court’s landmark decision in Rapanos
v. United Statesto the interrelated
fact patterns presented in Moses
and the Court’s two other post-Rapanos
decisions from this year—N.
Cal. River Watch v. City of Healdsburg and San
Francisco Baykeeper v. Cargill Salt Division.[4]
Decades of Discharges and Regulatory Action
The record before the Ninth Circuit revealed that
beginning in the 1980s, and continuing for more than 20 years
thereafter, the defendant, Charles Moses, used heavy equipment to
reroute and reshape Teton Creek, a seasonally intermittent stream that
flows two months out of the year into the
Teton River
and, ultimately, the
Snake River
.[5] Over approximately two decades, Moses moved tons
of gravel and other material, and erected log and rock structures within
the seasonally intermittent stream.
As early as 1982 and several times thereafter,
U.S. Army Corps of Engineers (“Corps”) officials warned Moses that
his work altering Teton Creek required a permit under the CWA. Claiming
that his activities were outside the jurisdiction of the Corps, Moses
refused to obtain a permit. As a consequence, the Corps ordered Moses in
1995 to stop all dredge and fill operations in the creek. The Corps sent
Moses follow-up letters in 1996 and 1997, and issued him a notice of
violation (“NOV”) in December 2002.
Despite the repeated warnings of the Corps and the
notice of violation, Moses continued to periodically dump material in
Teton Creek. Eventually, the Environmental Protection Agency (“EPA”)
stepped in and issued Moses a CWA cease and desist order.[6] Even with the involvement of another federal
regulatory agency Moses continued to ignore the orders of both agencies
and remained adamant in his refusal to apply for a permit under the CWA,
all the while continuing to contract for work to be performed in Teton
Creek (primarily during no flow periods).
"Overall,” the Court noted, "thousands
of cubic yards of gravel and other materials were moved, and the channel
was deepened, widened, and greatly disturbed. The disturbance reached
both upstream and downstream of the work perpetrated by Moses and his
minions."[7]
The Conviction and Defense
In March 2005, a federal grand jury indicted Moses
for “felonious violation of the CWA for knowingly discharging, and
causing to be discharged, pollutants from a point source or point
sources into waters of the
United States
without a
permit.”[8] The district court sentenced Moses to 18 months
imprisonment, one year of supervised release, and imposed over $9,000 in
fines and special assessments.
Moses appealed, asserting two primary defenses.
First, he claimed that the portion of the creek that he worked in did
not constitute “waters of the
United
States
” and
that the federal agencies lacked jurisdiction to prosecute him. Second,
Moses asserted that even if he had caused a discharge into waters of the
United
States
, the
discharge did not require a permit because his work within the streambed
occurred during periods of no flow.
The Court’s Analysis
Waters of the
United
States
The Ninth Circuit framed the question as
"whether a seasonally intermittent stream which ultimately empties
into a river that is a water of the
United
States
can,
itself, be a water of the
United States
."[9] In rejecting Moses’ defense, the Court cited
its own pre-Rapanos
precedent, Headwaters v. Talent
Irrigation District, wherein the Ninth Circuit affirmed the
view that intermittent tributaries—intermittently flowing irrigation
canals—constitute waters of the
United
States
.[10] The Court found additional support in the Supreme
Court's discussion of tributaries and intermittent streams in Rapanos,
wherein the Supreme Court failed to find majority support for a single
test to determine federal jurisdiction under the CWA.[11] Concluding, as it has before, that the
controlling test of CWA jurisdiction is Justice Kennedy’s concurring
opinion in Rapanos,[12] rather than Justice Scalia’s plurality opinion,
the Ninth Circuit summarized Rapanos
as not ruling out jurisdiction for “seasonal rivers which contain
continuous flow during some months of the year but no flow during dry
months,” but rather recognized that “the Corps can reasonably
interpret the Act to cover the paths of such impermanent streams.”[13] Accordingly, the Ninth Circuit concluded that the
Supreme Court in Rapanos “unanimously
agreed that intermittent streams (at least those that are seasonal) can
be waters of the
United States
.”[14]
Discharge
The court characterized its rejection of Moses’
second defense as being based on “common sense:” “The mere fact
that pollutants are deposited while … Teton Creek is dry cannot
make a significant difference,” “especially when the Corps retains
jurisdiction.”[15] The Court refused to hold otherwise because such
an interpretation of the CWA would “countenance significant pollution
of the waters of the
United States
as long as
the polluter dumped the materials at a place where no water was actually
touching them at the time.”[16] The Court also recognized the fact Moses had
“create[d] a situation where pollutants … remained in Teton
Creek when the water rose within it,”[17] and “when the water flowed, materials dislodged
by Moses’ operations would [also] be carried downstream.”[18]
Lessons Learned Through ‘Courage or
Foolhardiness’
The Ninth Circuit concluded by chiding Moses for
choosing “to ignore all demands by the EPA and the Corps that he
comply with the Clean Water Act … And while his sang-froid (or
even contempt) in the face of agency demands may show either courage or
foolhardiness, it does not save him from the consequences of his
actions.”[19] In addition to serving as a reminder of the
potential criminal penalties available to EPA under the CWA, the Moses
decision is significant for its application of Rapanos
to intermittent streams.
In fact, prior to its ruling in Moses,
the Ninth Circuit appeared potentially unwilling to construe Rapanos
as applying to such waterways.In a ruling earlier this year, the Ninth
Circuit in Cargill
actually seemed to be narrowing the scope of Rapanos
to only cases involving adjacent wetlands while excluding
other bodies of water that might have a nexus with a navigable-in-fact
waterway.[20] Specifically, the Cargill opinion stated that in Rapanos, “[n]o Justice, even in dictum, addressed the
question whether all waterbodies with a significant nexus to navigable
waters are covered by the Act.”[21] With its analysis and holding in Moses,
the Ninth Circuit appears to have backed away from drawing
such a bright line in applying Justice Kennedy’s test from Rapanos,
and displayed a willingness to extend the significant nexus
analysis to water features—such as seasonally intermittent
streams—other than merely adjacent wetlands.
Nevertheless, the Ninth Circuit failed to
explicitly reconcile this case with Cargill.
The court also did not take the opportunity to bring further clarity to
how it construes Rapanos by
discussing the commonalities and distinctions between this case, and the
recent Healdsburg and Cargill
opinions. This is striking not only due to the interrelated issues
presented by each of these cases, but also because earlier this year the
Ninth Circuit withdrew the Healdsburg
decision in an attempt to clarify it in the context of Cargill[22] (and then filed the revised Healdsburg
opinion only three days after it filed the Moses
opinion).
Based on Moses,
it is safe to assume that in the Ninth Circuit the CWA’s dredge and
fill provisions apply to most, if not all, intermittent streams. For
other types of waterbodies, however, property owners, contractors, and
developers will need to parse the Ninth Circuit’s and the Supreme
Court’s CWA opinions to try and figure out whether the water feature
is subject to CWA jurisdiction prior to conducting activities that will
result in the discharge of fill material therein.
For more information on the Clean Water Act,
contact Aaron Courtney in the Marten Law Group’s
Portland
,
Oregon
, office or
Jeff
Kray in the
Seattle
,
Washington
, office.
[1] 496 F.3d 984 (9th Cir. 2007).
[2] The CWA prohibits “the discharge of any
pollutant” (including “dredged spoil … rock [and] sand”)
into “navigable waters,” which in turn means “waters of the
United
States
.” 33
U.S.C. §§ 1311(a), 1262(6), 1362(7), 1362(12), and 1362(16).
[3] 126
S. Ct.
2208
(2006).
[4] 457 F.3d 1023 (9th Cir. 2006) and 481 F.3d 700
(9th Cir. 2007), respectively. For an in-depth discussion of the Ninth
Circuit’s failure to bring clarity to how it construes Rapanos,
see this newsletter’s
September 12, 2007
article Clear
as Mud: Newest Ninth Circuit Case Interpreting Rapanos Test for Clean Water
Act Jurisdiction Offers Little Clarity.
[5] An upstream, man-made diversion controlled flow
in the creek, which at times could be “torrential.”
[6] 33 U.S.C. § 1319(a).
[7] 496 F.3d at 986-987.
[8]
Id.
at 987.
[9]
Id.
at
989.
[10] 243 F.3d 526 (9th Cir. 2001).
[11] 126
S. Ct.
at 2215.
[12] The court’s conclusion on this point followed
Ninth Circuit precedent described in two earlier articles in this
newsletter regarding Healdsburg:
Clear
as Mud: Newest Ninth Circuit Case Interpreting Rapanos Test for Clean Water
Act Jurisdiction Offers Little Clarity and Ninth
Circuit, In First Case Applying Supreme Court’s Rapanos Decision,
Holds NPDES Permit Required for Sewage Discharge to Excavated Pit.
[13] 496 F.3d at 990.
[14]
Id.
at
991.
[15]
Id.
[16]
Id.
[17] The court also recognized the long-established
interpretation of the statute that “simply dredging up and
redepositing what was already there is sufficient to run afoul of the
CWA.”
Id.
[18] Id.at
993.
[19]
Id.
[20] 481 F.3d 700. See
also Ninth
Circuit Declines to Extend CWA Jurisdiction to “Adjacent Waters”
Other Than Wetlands.
[21]
Id.
at
710.
[22] See
this newsletter’s article noted supra
note 3
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
NOTE: In accordance with Title 17 U.S.C. section 107, any copyrighted
material herein is distributed without profit or payment to those
who have
expressed a prior interest in receiving this information for
non-profit
research and educational purposes only. For more information go
to: http://www.law.cornell.edu/uscode/17/107.shtml
Source:
http://www.martenlaw.com/news/?20071010-intermittent-streams
|