
The Bureau of Reclamation’s
Capability to Fulfill Its Core
The Customer’s Perspective
A Compilation of Case Studies
from Five Western States
Submitted to:
National
Research Council
Board
on Infrastructure and the Constructed Environment
Committee
on Organizing to Manage Construction and Infrastructure
in
the 21st Century –
Bureau
of Reclamation
June 2005
The Bureau
of Reclamation’s Capability to Fulfill Its Core
The
Customer’s Perspective
Executive
Summary
The
Family Farm Alliance (
The
Several contributors to this report observed that Reclamation has carried out few major new construction projects during the past decade, and as a consequence, the agency’s engineers and construction management staff lack practical construction experience. The designers and builders of Reclamation’s most impressive works have long since retired, and the current generation of engineers, planners and managers has not had the opportunity to develop the skills of their predecessors. Moreover, many contributors believe that Reclamation has too few licensed engineers.
Despite
these negative findings, there is also evidence that Reclamation staff members
from regional and area offices can play a key role in helping to find the right
path to make multi-agency processes and projects work. When strong relationships
are developed between Reclamation employees (especially in area or regional
offices) and local water users, strong, cooperative and innovative solutions can
be reached. There are other models in the West – such as implementation of
water project grant and loan programs by California’s Department of Water
Resources – where successful projects have been completed. A template for
success might be one where state and federal agency regulators establish
criteria, funding agencies write the checks, and local districts and their
consultants implement and satisfy regulatory criteria and funding eligibility
requirements.
Meeting the challenge of modernizing the West’s aging water infrastructure will require a corps of highly qualified professionals serving in the public and private sectors. The Bureau of Reclamation must either hire skilled and experienced engineers and managers, or turn to the private sector to provide the human resources necessary to maintain and improve the Bureau’s facilities.
The Family Farm Alliance looks forward continuing to work with the Committee, and the Bureau of Reclamation to ensure that water users who pay for Reclamation's services get real value for their investment.
Table of Contents
Staff members from Reclamation regional and area
offices played
key
roles in helping to find the right path to make this process work.
Absent
cooperative efforts of Reclamation staff, much of the land
served
by the Water Company would not have been able to
continue
in agricultural production.
After
an unsatisfactory experience working with the Technical Services
Center,the
District has concluded that it will
contract with qualified
private
civil engineers for work on a reservoir outlet project.
While
title transfers are viewed by many as a positive means of strengthening
control
of water resources at the local level, the District continues to meet
challenges
with Reclamation in this process.
Over
the past nine years, the District has been faced with the challenge
of
absorbing unanticipated expenditures caused by Reclamation cost
overruns
on the Cachuma Project.
The
District has incurred costs from flawed Reclamation structural design
work,
and now that the District has hired private professional engineers,
Reclamation
insists that the District pay Reclamation for plan review.
Local
water users believe that Reclamation has been sensitive to keeping
operation
and maintenance costs to a minimum.
These programs might provide a model that
Reclamation should consider
employing:
less bureaucracy and more on-the-ground improvements.
Local
entities take the lead on projects and come in under-budget and on time.
Introduction
The
National Research Council (NRC) has been asked by the U.S. Interior Department
to advise the Bureau of Reclamation (Reclamation) on the organizational,
management, and resource configurations that will provide Reclamation with the
capability to fulfill its core mission. A committee of the NRC Board on
Infrastructure and the Constructed Environment is actually conducting the study.
The committee is comprised of academics, agency officials, and engineers from
the private and public sector, and is chaired by Dr. James K. Mitchell,
Distinguished Professor Emeritus at Virginia Polytechnic Institute. The
committee has also been tasked with identifying any additional capabilities that
Reclamation should possess in order to fulfill its core mission. The Family Farm
Alliance has prepared nine case studies and related observations in hopes that
this process may help to ensure that water users are being served in a most
cost-efficient manner.
The
Bureau of Reclamation’s Core Mission
The
Bureau Reclamation’s core mission is to provide for the delivery of water and
power from its facilities in a manner that meets applicable requirements of
state and federal law. Essential Components of the core mission are: 1)
providing for the operation and maintenance of existing facilities that are
likely to remain in federal ownership; 2) providing for the rehabilitation and
replacement of infrastructure that is likely to remain in federal ownership; and
3) possessing the ability to manage the construction of new projects that
Congress may fund through Reclamation.
The
NRC Committee’s Statement of Task
The
Board on Infrastructure and the Constructed Environment Committee on Organizing
to Manage Construction and Infrastructure in the 21st Century –
Bureau of Reclamation has been tasked with the following:
This
study is sponsored by the Department of Interior, Bureau of Reclamation. It
started
About the Family Farm
The Family Farm Alliance is a nonprofit organization composed of
family farmers and those in related industries throughout the Western states
dedicated to the preservation of irrigated agriculture. The organization was
formed to ensure that its members are afforded an opportunity to air their views
and concerns to the public, to legislators, and to regulators.
The
The Family Farm Alliance
strongly supports the focus of Reclamation on fulfilling its core mission of
delivering water and power in accordance with applicable contracts, water
rights, interstate compacts, and other requirements of state and federal law.
Inherent in this definition of core mission is the need to prioritize the
expenditure of federal funds and other resources of the Department of the
Interior. Reclamation’s Water 2025
Program, so long as it continues to recognize that transfers and the use of
market mechanisms must be voluntary and pursuant to state law, provides a strong
foundation for defining the role of the Bureau in meeting future water needs of
the West.
In the late 1990’s, the Family
Farm Alliance took a lead role in an effort that was designed to address
concerns of districts that contract with the Bureau of Reclamation regarding
expenses and overhead that were assigned by Reclamation to work that was paid
for by the water users. With the cooperation of the Bureau of Reclamation
in general, and Jack Garner in particular, great progress was made in this
regard. While that effort was a
partial success, several water districts in the West have recently experienced
one or more problems, some of which are detailed in the following case study
examples. There are also instances where Reclamation has strongly contributed
leadership as well as funding assistance that led to effective local solutions
to water management challenges. Finally, we have several examples of success
stories that have taken place, with local irrigation districts taking the lead
on major construction projects. There are important lessons that may be learned
by studying these examples that may apply to how Reclamation does business in
the future. The case studies that
follow provide further detail on this matter.
CASE STUDY
#1:
Staff
members from Reclamation regional and area offices played
key roles in helping to find the right path to make this process work.
The Sacramento River Basinwide
Management Plan (BWMP) was prepared by the Sacramento River Settlement
Contractors (SRSC) with assistance and input from the U.S. Bureau of Reclamation
(Reclamation) and the California Department of Water Resources (DWR). The BWMP
was prepared to meet the requirements of the January 1997 Memorandum of
Understanding between the Settlement
Contractors and the
Staff members from Reclamation
regional and area offices in northern
The BWMP process has been a
successful, cooperative effort among the SRCSs, Reclamation, and DWR, as
evidenced by the following:
v
The BWMP process provided
for an open dialogue and increased understanding of the water resources issues
facing the
v
The BWMP process provided
a technical forum for addressing the different methodologies of water resources
management and the associated technical issues.
v
The BWMP process provided
the necessary data and background to allow the ultimately successful completion
of the contract renewal process.
v
The BWMP process provided
the framework for the subsequent development of the successful Phase 8
negotiations to the Bay-Delta Water Rights Hearings.
The
BWMP process was a lengthy endeavor (1998-2004). However, the project objectives
that were established for the BWMP process were successfully met. Sufficient
background information has been developed on the water resources management
issues affecting the
Appropriate
measurement practices, drainwater management, system improvement, and
conjunctive management projects are being developed in cooperation with DWR and
Reclamation and submitted for potential funding. The data and relationships
developed in the preparation of the BWMP are continuing to foster improved water
management across the
Contact:
Senior Water Resources Planner
CH2M Hill
(530)-243-5831
Email: moliver@ch2m.com
CASE STUDY #2: Colusa Drain
Mutual Water Company (Water Company)
Absent
cooperative efforts of Reclamation staff, much of the land served by the Water
Company would not have been able to continue in agricultural production.
The
Water Company was organized on
The Water Company’s contract is a replacement contract that
does not provide for direct delivery of CVP water to the Water Company members.
The contract authorizes the Water Company to divert water from the Colusa
Basin Drain during those times when the Water Company’s and its members’
water rights are deficient in exchange for payment to the United States for CVP
water released to the Sacramento River on behalf of the Water Company to ensure
senior downstream water right holders remain whole.
Unfortunately for the Water Company, there has been a significant
reduction in return flows accruing to the Drain as a result of upstream
environmental restrictions on water diversions and implementation of water
conservation programs by neighboring Settlement Contractors.
As a result, in many years the Water Company suffers from inadequate
water supplies during the summer months and has had to arrange, through annual
transfer agreements with neighboring Settlement Contractors, for other
supplemental water supplies to be delivered to the Colusa Basin Drain.
The inadequate water supplies resulted in reduced yields due to the high
salt content of the water in the Colusa Basin Drain.
The impact of the transfers with neighboring Settlement
Contractors is essentially a change in the way the Water Company pays for its
water. If there were sufficient
flows in the Colusa Basin Drain, the Water Company would pay the
Since 1997, Reclamation has worked cooperatively with the Water Company and neighboring Settlement Contractors to effect these annual transfers. These transfers have provided the Water Company with a reliable, affordable, and quality supply of water. Absent these cooperative efforts, much of the land served by the Water Company would not have been able to continue in agricultural production.
Contact:
MBK Engineers
(916)-456-4400
Email: vancamp@mbkengineers.com
CASE STUDY
#3: Northern Colorado Water Conservancy District
After
an unsatisfactory experience working with the TSC, the District has concluded
that it will contract with qualified private civil engineers for work on a
reservoir outlet project.
The
Northern Colorado Water Conservancy District (District) since 1999 has been
working to complete a project that would add an outlet to Carter Lake Reservoir.
The objective of the District has been to complete this project by April 2007 in
the most cost-effective manner possible with a total cost not to exceed $10
million. The District has spent considerable time and resources working with the
Bureau of Reclamation (Reclamation) Technical Services Center (TSC) in
There
are four reasons why the District is requesting that TSC no longer have a lead
role in the engineering, design and construction management of this project:
This
latter concern raises several policy questions. Is it the policy of Reclamation
to require that TSC perform design work? If so, is this a Reclamation-wide
policy? From a policy perspective,
the District believes there is no reason to depart from the historic model that
has existed for projects of this nature associated with the Colorado-Big
Thompson (C-BT) Project. The
Contact:
Eric Wilkinson
General Manager
Northern Colorado Water Conservancy District
(970)-532-7700
Email: ewilkinson@ncwcd.org
CASE STUDY
#4: Pershing County Water
Conservation District
While
title transfers are viewed as a positive means of strengthening control of local
water resources, the District continues to meet challenges with Reclamation in
this process.
Pershing County Water
Conservation District (District) is located in Lovelock, in northwestern
While
title transfers are viewed by many as a positive means of strengthening control
of water resources at the local level, the District continues to meet challenges
with the Bureau of Reclamation in this process. Many of the District’s
concerns are similar to other case studies in the West which revolve around
design-and-build functions of Reclamation. Key concerns and observations of the
District include:
1.
Reclamation required that
design work be performed by Reclamation staff and an apparent unwillingness
to consider allowing this work to be performed in conjunction with the Districts
or qualified consultants. For example, neither the District nor it’s
consultant were permitted to be involved in the process of developing the
cultural resources compliance required as part of the title transfer.
Reclamation after two years has outlined a process that for the initial phase
alone will cost $960,000. Notably, this is after the District had already
completed an extensive Environmental Impact Statement (EIS).
2.
Cost estimates for work
that are significantly over the reasonably anticipated costs, including
estimates from qualified consultants (see above). This is particularly true for
cultural resources activities.
3.
A need to improve contract
management. In the District title transfer, a portion of the lands will be
conveyed to the State of
4.
Lack of recourse by the
District to fully understand and engage in decision-making and related cost
estimates. The District believes it has little control of what Reclamation
will decide to spend title transfer funds on with respect to cultural resources,
even though the District is responsible for one-half of these costs.
5.
A need to improve
"turn-around" times for design work or decisions. For
example, relative to the EIS mentioned above, Reclamation promised a one-year
turn around. The District is now into the process at least two years, and
that time period may have been even more prolonged if the District had not bid
out the National Environmental Protection Act contractor under State law.
As to the aforementioned cultural resources initial process document, the
District was initially promised it would be wrapped up within months; the
process has now extended to over a year and a half.
The District is proud of its partnership and working relationship with Reclamation, and is hopeful that these challenges can be constructively and timely addressed as the title transfer moves to conclusion.
Contact:
Schroeder Law Offices
(503) 281-4100
Email: las@water-law.com
CASE STUDY #5: Santa Ynez
River Water Conservation District
Over
the past nine years, the District has been faced with the challenge of absorbing
unanticipated expenditures caused by Reclamation cost overruns on the Cachuma
Project.
The
Santa Ynez Water Conservation District (District) serves rural agricultural,
domestic and commercial customers on 10,850 acres in
The
District has four water sources: the major source is the federally-owned Cachuma
Project, which provides 43% of supplies. The District’s heavy dependence on
the Cachuma Project requires that it be vigilant about protecting that water
source and the costs incurred by it. The District has four other local partners
in the Cachuma Project: the City of
Over
the past nine years, the District has been faced with the challenge of absorbing
unanticipated expenditures caused by cost overruns on the Cachuma Project. These
cost overruns have been significant and, in the District’s opinion, avoidable.
The District has gone so far as to request Congressional assistance in two
objectives: (i) bringing about structural reforms in the Bureau of Reclamation
to improve that agency’s ability to plan and carry out water projects, and
(ii) providing financial relief to the local water customers who end up paying
for Reclamation’s miscalculations. Four specific examples of cost overruns
follow:
Bradbury
Dam Seismic Strengthening Project – Between 1994 and 2001, Reclamation
designed and substantially completed a major project to strengthen Bradbury Dam
at the downstream end of
Congress
allocated $41.5 million for the project, based on a report submitted by
Reclamation. The construction cost for the project was completed 15% below the
budget amount. Yet, amazingly, total costs were 18% over budget, caused entirely
by an 82% overrun in the Contract Administration and Design & Specification
functions. The latter cost more than doubled, from $2.5 million to $6.24
million.
Hilton
Creek Project – When Reclamation designed the Bradbury Dam SOD
modifications (see above), environmental mitigation was expected to cost
$500,000. During construction, the scope of mitigation increased to include the
Hilton Creek Project, and the cost estimate has now escalated to over
$3,928,000. The original Hilton Creek Project as designed and constructed by
Reclamation did not work as engineered and had to be redesigned.
Hilton
Creek is a small tributary that enters the main stem of the Santa Ynez River
just downstream of the “stilling basin” located at the base of Bradbury Dam.
The Hilton Creek Project is a mitigation measure for the loss of habitat (a
fraction of an acre) in the stilling basin caused by the Seismic Strengthening
project. It has also proved essential to Cachuma Project operations.
The
Hilton Creek project is simple in design: water gravity flows or is pumped from
Release
Gate Maintenance Project –As the owner and operator of the Cachuma
Project, Reclamation makes decisions about the maintenance of these facilities.
However, the maintenance costs are paid by the water users that receive Cachuma
water. Since these expenses constitute O&M (not capital costs), these
expenses cannot be capitalized and repaid over a term of years. Thus, a cost
overrun in a maintenance project can have a significant adverse impact on a
small contracting agency’s annual budget.
Water
spills from the Cachuma Project through a set of large radial gates and a
spillway. In 1997, Reclamation determined that the radial gates needed to be
repainted. The work was recently completed at a cost of $3.0 million, which is
67% higher than its original cost estimate of $1.8 million. Part of the increase
resulted from the fact that extensive areas on the gates were found to have
asbestos-based paint, which required far greater effort and cost for removal due
to OSHA and environmental regulations.
The
District has one key, outstanding question: Since Reclamation applied the
original asbestos-based paint to the gates in 1976, why wasn’t this fact known
to Reclamation when it designed the repainting job and the technical
specifications for the project?
Flashboard
Installation Project – Reclamation has completed additional structural
improvements to the Bradbury Dam radial gates which make it possible for
Reclamation to utilize three feet of the flashboard extension to surcharge and
accumulate a larger quantity of water in the lake during high flow periods.
These flows ultimately benefit public trust resources, specifically endangered
steelhead / rainbow trout downstream of Bradbury Dam. Other benefits included
reduced flood risks to downstream properties and urban areas.
This project has also experienced a cost overrun. The original Reclamation estimated cost for this project was $118,650. The actual cost is $531,700, which is 448% above the original estimate.
Contact:
Manager / Secretary
Santa Ynez River Water Conservation District
Improvement District No. 1
(805)-688-6015
Email: cdahlstrom@syrwd.org
CASE STUDY
#6: Hermiston Irrigation District
The
District has incurred costs from flawed Reclamation design work, and now that
the District has hired it’s own engineers, Reclamation wants the District to
pay for plan review.
In
the mid 1990’s, Hermiston Irrigation District (District) participated in a
safety of dams update to its facilities in northeastern
As
predicted by the District, numerous operational problems over the next three
years led to a revised design of the structure, which the District was required
to pay for as part of the safety of dams expense. The cost of the
modification was $115,000, including engineering design. Importantly, 55 percent
of the price tag was attributed to engineering costs generated by Reclamation
staff.
More recently, Reclamation has required that the District replace an inlet drop structure that feeds the District reservoir. Although the District has hired registered professional engineers to perform the analysis and engineering for this replacement, Reclamation insists that the District contract with them to have these plans reviewed – at District cost. Finally, the District to date has not received a detailed cost accounting for Reclamation’s expenses incurred in the safety of dams process.
Contact:
Chuck Wilcox
Manager
Hermiston Irrigation District
(541)-567-3024
Email: hid@eoni.com
CASE STUDY
#7:
Local
water users believe that Reclamation has been sensitive to keeping operation and
maintenance costs to a minimum.
The
Idaho Water Users Association report that operations and maintenance costs of
dams and pumping plants by the Bureau of Reclamation Snake River Area Office (
Consider
the following close-out operations and maintenance expenditures for Calendar
Year 2004 in the Snake River Area Office:
|
Facility |
CY 2004 Budget |
CY 2004 Actual
Expenditures |
|
|
$
403,311 |
$
392,311 |
|
Arrowrock
Dam |
$
496,044 |
$
519,413 (Note #1) |
|
|
$
308,030 |
$
254,350 |
|
Cascade
Dam |
$
537,292 |
$
318,079 |
|
Deadwood
Dam |
$
237,230 |
$
292,821 (Note #2) |
|
Primary
Pump |
$
75,028 |
$
44,344 |
|
TOTAL |
$2,056,935 |
$1,821,318 |
Note #1: A five percent overrun occurred
to accommodate expedited work on the installation of electronic security
monitoring at the facility.
Note #2: The overrun was attributed to
unforeseen chimney, foundation and roof stabilization required on the main cabin
and generator / storage building.
Because
the Snake River Area Office came in $235,617 (or 11.5 %) under budget on these
O&M items, the local irrigation districts received a substantial credit for
the calendar year.
Similar
experiences have been reported by Minidoka Project spaceholders, which include
Twin Falls Canal Company, Northside Canal Company, Milner Irrigation District,
and American Falls Reservoir District. Local water users believe that the Bureau
of Reclamation has been very sensitive to keeping operation and maintenance
costs to a minimum for its stakeholders.
For
example, at American Falls Reservoir, spaceholders have an obligation to pay
erosion control costs for work at the Reservoir. Reclamation arranged for
contracts with water user entities to accomplish the work rather than bid the
work to private contractors. The annual saving to the spaceholders exceeds
$100,000 in most years.
Elsewhere
in the region, spaceholders in the late 1990’s were advised that the channel
of Pilgrim Creek, a tributary of Jackson Lake Reservoir, was shifting. Because
of Clean Water Act regulations, and due to a change in jurisdiction to the U.S.
Army Corps of Engineers’
The
Bureau of Reclamation has also been proactive in working with local interests to
facilitate O&M work. Reclamation cooperated with local water users to reduce
flows so private owners of the Banbury Springs Pipeline owners in the Hagerman
Reach of the
Contact:
Norm Semanko
Executive Director
(208) 344-6690
Email: norm@iwua.org
CASE STUDY
#8: State of
These
programs might provide a model that Reclamation should consider employing: less
bureaucracy and more on-the-ground improvements.
In
recent years, driven primarily by voter-approved bond measures, the State of
Many
their
specific needs and can incrementally improve water supply without drawing the
attention of environmental show-stoppers like major new storage projects. In a
similar federal program, there has been a tremendous level of interest West-wide
in the Water 2025 Grant Program administered by Reclamation, and it is
disappointing to many that Congress this year may zero those funds out.
In
Water
users in the
The
DWR programs might provide a model that Reclamation should consider employing:
less bureaucracy and more on-the-ground improvement.
Contact:
Dick Moss
Vice President, Water Resources
Provost & Pritchard Engineering Group
3500
(559)-636-1166
Email: RMoss@ppeng.com
CASE STUDY
#9:
Local
entities take the lead on projects and come in under-budget and on time.
An
impressive array of ecosystem restoration activities has been undertaken in the
[1].
The use of water within the
As
remarkable as this broad array of completed projects is, what is also impressive
is the high level of performance shown by local water districts to deliver these
projects in a timely manner, and often under budget. In the instances shown
below, ample evidence supports the argument that local districts and their
consultants demonstrate superior project management performance when viewed in
terms of project delivery parameters like time from start to finish, estimated
vs. actual costs, achievement of regulatory compliance goals, avoidance of
long-term impacts on water users, disputes and lawsuits, etc. A few examples of
Anderson-Cottonwood
Irrigation District (ACID),
Western
Canal Water District Butte Creek Project, near
Reclamation
District 108 Fish Screen, Sacramento River – RD 108, acting as lead on this project, secured 99% of the $11
million cost with outside funding. The final project was completed $1 million
under budget and on schedule. Feasibility study, preliminary design, final
design, cost estimates, and implementation plan were completed by the
district’s consultants in ten months.
Under
CALFED and state matching funds programs, much of the project work outlined
above was performed through district-led efforts, because several grant sources
were used to fund individual projects. In each of these cases, the districts
took the lead, engaging their own resources and those of their consultants in a
way that best suited their needs, and taking on the coordination role with the
funding and regulatory agencies. A unifying theme noted in all of these examples
is this: results that are compatible with local needs are more readily
achievable when there is local control.
The
responsibilities and accountabilities (by the involved parties and specific
individuals) when federal agencies are involved with water projects often change
over time, whereas local irrigation districts can accept responsibility and
accountability for completing projects from Day One. When responsibilities shift
from desk to desk within agencies, it is difficult to achieve efficiency or
sustained progress toward a solution. On the other hand, if a local entity and
specific person can provide continuity, leadership, and is motivated to sustain
progress and accountability in achieving a defined outcome, real project
management efficiency can be realized. If federal agencies are changing roles
and responsibilities, and if agency personnel change over time, it is difficult
to maintain progress on projects that can take several years to complete.
In
the examples noted above, the agency regulators set the criteria, the funding
agencies wrote the checks, and local districts and their consultant and
contractors addressed and satisfied the regulatory criteria and funding
eligibility requirements. Keeping the accountability and responsibility
centralized is key to getting projects done on time, and under budget.
Contact:
Director of Member and Government Affairs
455 Capitol Mall,
(916)-442-8333
Email: tmanley@norcalwater.org
Findings
The
case studies in
The
Family Farm Alliance is committed to constructively working with Reclamation,
the Department of Interior, and Congress to address these concerns. As
illustrated in the
Conclusions
As is recognized by Secretary Norton’s Water 2025 Initiative, it is imperative that Reclamation provide for the operation, maintenance, and modernization of existing water supply infrastructure. Many Reclamation facilities are approaching the end of their design life, and some are well past that point. Many of these facilities need to be replaced with modern designs that provide for greater water management efficiency. Sound business practice dictates that this existing infrastructure, and the water supply it conveys, be preserved prior to the dedication of scarce resources to the development of new supplies.
Meeting
the challenge of modernizing the West’s aging water infrastructure will
require a corps of highly qualified professionals serving in the public and
private sectors. The Bureau of
Reclamation must either hire skilled and experienced engineers and managers, or
turn to the private sector to provide the human resources necessary to maintain
and improve the Bureau’s facilities.
Several contributors to this report observed that Reclamation has carried out few major new construction projects during the past decade, and as a consequence, the agency’s engineers and construction management staff lack practical construction experience. The designers and builders of Reclamation’s most impressive works have long since retired, and the current generation of engineers, planners and managers has not had the opportunity to develop the skills of their predecessors. Moreover, many contributors believe that Reclamation has too few licensed engineers.
The
lack of engineering experience and expertise within Reclamation is cited by
several contributors to this report as the primary cause of the problems
outlined in the case studies. It is
also the reason why some irrigation districts are increasingly opting to pay
additional money to outside consultants who do have that experience and
professional training.
Now, in some cases, Reclamation employees are insisting that they review plans that have already been developed by professional engineers, and water users are being asked to pay for these reviews after already having paid outside consultants to develop the plans. Reclamation’s approach in this regard is seen as archaic by water users. They question why they must continue to pay people to look over their shoulder.
As
demonstrated in the
Other
Recommendations
It
is not wise to offer up recommendations that can be applied “across the
board”, especially when water resources issues are so diverse and distinct,
depending on the location. However, the management approaches noted in some of
the positive examples included in this summary should be considered as options
that might be employed, where applicable, in other parts of the West.
Contributors
to this report have offered a number of additional recommendations that are
outside the scope of this Committee’s charge.
Nevertheless, these recommendations, if carried out, would substantially
improve the Bureau of Reclamation’s performance. They include:
1.
Congressional committees should conduct oversight hearings to
review Reclamation’s project planning operations, with particular attention to
the design and construction management functions based in
2. Expand the Water 2025 matching grant program to provide additional opportunities for the investment in water conservation and efficiency measures; and
3. Develop additional funding mechanisms that will enable water users to access alternative sources of capital in order to repair and modernize existing infrastructure:
v Reinvigorate the Small Project Loan Program
v
Develop federally backed loan guarantees
v
Continue the historical use of
zero interest loans already authorized by law.
v
Allow entities with annual
repayment obligations to shift those obligations to operation, maintenance and
replacement (OM&R) reserve accounts.
v
Allow for the capitalization
of OM&R.
The
SOURCES OF
INFORMATION
1
For a more complete assessment of the myriad of fish passage projects undertaken in the Sacramento Valley, please refer to “Status of Fishery Programs in the Sacramento Valley”, February 2002, Northern California Water Association, Sacramento, California.