Dike break fallout goes on

 
H&N photos by Andrew Mariman
Mike Gehon, a foreman who works for farmer Ron McGill, talks about plans to use two 1,147-gallon propane tanks from Chiloquin to salvage farm equipment Monday from floodwaters on Upper Klamath Lake.
 

July 18, 2006

Farm equipment recovery begins

By TY BEAVER

H&N Staff Writer

Farmer Ron McGill and three of his hired men waded into the newest part of Upper Klamath Lake Monday to retrieve farm equipment submerged in up to 10 feet of water.

“There's no sense waiting,” said McGill, whose farmed land flooded June 7 when the Geary Canal dike failed.

Nearly six weeks after the dike failure on Upper Klamath Lake flooded more than 2,000 acres of land and closed Highway 140, questions linger about the future.

McGill and his wife, Ann, leased the flooded land, known as the Caledonia Marsh, and planted white wheat before the dike failed. They had planted 1,400 acres of 1,600 acres they leased, McGill said. Two-thirds of the flooded land is owned by Running Y Ranch. The other third is owned by the Geary Family Trust.

Some equipment already retrieved

Some pieces of equipment were retrieved before floodwaters moved in, but not all, Ron McGill said. Three ground rollers, an implement trailer and an excavator were among the pieces left behind.

On Monday McGill used a pontoon boat and a pair of empty tanks to salvage the farming equipment.McGill and his men were at the site yesterday attempting to salvage some of the equipment. The hollow rollers were removed by draining the water from them and floating them back to shore, McGill's foreman Mike Gehon said.

To remove the other equipment, the men sank two 1,147-gallon tanks and placed a tank under each piece of equipment. The tanks were then filled with air and floated the equipment to dry land.

“Just gotta take it one step at a time and be careful,” Gehon said.

McGill said some of the equipment will be reusable, but ball bearings, hydraulics and rams will be replaced and contaminated oil removed. Other pieces, however, are a lost cause, he said. The excavator, because of its electrical system, is probably useless.

Used for planting crops

The flooded equipment is the greater part of McGill's implements for planting crops. Without it, in a few weeks after harvest, his farming operation would be at a standstill, he said.

It is still unknown what will happen to the dike and flooded land. McGill said he did not think the water would be removed, and believes the area will be used as extra water storage.

Dave Kvamme., spokesman for Pacificorp, said because Pacificorp does not own the flooded land or the dike, the company cannot decide for itself how the situation will be resolved.

“We know this is going to take a while to sort out and hope everyone will cooperate,” he said.

Farmer says he contacted PacifiCorp about dike leaks

Ron McGill, who farms land flooded by the Geary Canal dike breach said he contacted PacifiCorp May 1 about leakage in the southern portion and “unprecedented cracks” in the northern portion.

Workers from PacifiCorp, the company in charge of maintenance on the dike, came to repair problems in the southern portion, but not the area with the cracks, he said.

The location of the breach is where the cracks were, he said.

Dave Kvamme, spokesman for PacifiCorp, said he could not confirm or deny McGill's call to the company regarding the dike.

“We have always responded appropriately when faced with problems with the dike,” he said.

Highway repair costs in millions

The cost of repairing flood damaged Highway 140 is estimated at $3 million, state officials said Monday.

A portion of the highway west of Klamath Falls closed June 7 after the Geary dike failed and water from Upper Klamath Lake flooded the road and more than 2,000 acres to the north.

Emergency repairs were done and the highway reopened a week later.

More work to raise the roadway by about 3 feet and add permanent concrete barriers and guardrails must be done soon to prevent flooding this winter and next spring, said Ron Snell, ODOT project manager. It's also believed flowing water could create unexpected, icy and treacherous driving conditions.

“Highway 140 is not designed to hold back water, therefore it cannot function as a dike or dam,” he said.

Snell termed the highway “a critical lifeline for many Klamath Basin residents and business owners.” Each day more than 4,000 trips are made over the damaged section of highway.

Snell said ODOT hopes to hire a contractor and begin construction work this summer with completion this winter.

Some farm equipment Ron McGill hopes to salvage is still partially submerged in floodwaters from Upper Klamath Lake.

+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
NOTE: In accordance with Title 17 U.S.C. section 107, any copyrighted
material  herein is distributed without profit or payment to those who have
expressed  a  prior interest in receiving this information for non-profit
research and  educational purposes only. For more information go to:
 http://www.law.cornell.edu/uscode/17/107.shtml


Source:  http://www.heraldandnews.com/articles/2006/07/18/news/local_news/local1.txt