
Levee
breach successful
Water now covers
2,500 acres, restoring wetlands for suckers
ABOVE: The
Williamson
River
delta, seen
here in August. BELOW: The same area, shown here this month, after the
levees were broken.
By
STEVE KADEL
H&N
Staff Writer
The
recent explosions that breached four half-mile sections of levee on the
Williamson
River
delta appeared to do their
job, successfully restoring wetlands for larval suckers, Nature
Conservancy officials said.
The
organization used 100 tons of explosives to remove the levees during a
series of blasts Oct. 30. By the following Saturday, water covered 2,500
acres at the river’s mouth that had served as agricultural land for
several decades.
Aerial
photos of the delta before and after breaching show a dramatic
difference in water cover. The wetlands restoration project was designed
to increase
Upper Klamath Lake
’s water storage capacity
by 17,000 acre feet — or about 6 million gallons.
Taking
samples
The
Nature Conservancy is collecting water samples to check for such things
as pH level, the amount of dissolved oxygen and levels of phosphorous
and nitrogen. Results are not yet available, said Matt Barry, project
manager for the Conservancy.
In
the spring, larval suckers will be studied to see how the new wetlands
“nursery” is being used.
“We
will be trying to see where they are and what condition they’re in,”
Barry said.
The
project’s goal was to restore five square miles of marshland to help
endangered suckers and improve water quality in the lake. If things go
as planned, larval suckers will spend more time in new wetlands habitat
before entering the lake, where predation is higher.
Larval
fish will be sent to
Oregon
State
University
to test their age, which
will indicate how long they stayed in the wetlands. Barry said tests at
OSU will measure the number of rings on the fishes’ bones — similar
to tree rings — to determine their age.
The
ambitious wetlands restoration project will cost about $10 million. The
next step is to break levees at
Goose
Bay
on the southeast portion of
the delta.
Dirt
instability
Explosives
were needed for the recent levee removal because the dirt wasn’t
stable enough to support heavy equipment. However, the
Goose
Bay
levees will be taken out by
traditional method instead of with explosives because the area becomes
dry during summer.
Barry said
Goose
Bay
has about 2,200 acres to be
flooded. Water level will be lower there than other areas of the
wetlands, possibly offering optimum habitat for fish.
“That’s the side I think will be better for larval
suckers,” Barry said.
The wetlands program is two years ahead of schedule,
he said, due in large part to fast levee removal work by LTM Inc. of
Klamath Falls
. The company removed more
than 1 million cubic yards of dirt in 2006. Ten yards of dirt is
considered a standard dump truck load.
“We under-estimated the ability of a good contractor
to move dirt,” Barry said of LTM. “They geared and had 25 or 30 guys
out there every day. They did a wonderful job.”
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
NOTE: In accordance with Title 17 U.S.C. section 107, any copyrighted
material herein is distributed without profit or payment to those
who have
expressed a prior interest in receiving this information for
non-profit
research and educational purposes only. For more information go
to: http://www.law.cornell.edu/uscode/17/107.shtml
Source:
http://pioneer.olivesoftware.com/Daily/Skins/heraldandnews/
navigator.asp?skin=heraldandnews
|