
Questions
& answers
Miscellaneous
questions
Klamath Falls
Herald and
News
April 4,
2008
Page C6
Q: What about other river systems, such as the
Trinity? Why were they not included in the settlement?
A: Siskiyou County Commissioner Jim Cook said he
suspects stakeholders limited the discussion to just the
Klamath
River
to placate
tribal members. He said including other river systems might have created
complications because some tribes, such as the Hoopas, have concerns
with rivers other than the Klamath. “I am glad they didn’t try to
force a Basin-wide solution.”
Greg Addington of the Klamath Water Users Association
said the Trinity “has its own somewhat unique legal history and
circumstances” and its own restoration program.
Klamath Tribes attorney Bud Ullman said the Trinity is
the subject of a separate settlement based on a “Record of Decision”
stemming from lengthy federal, state and tribal research and
negotiation.
“The Trinity has a unique history and setting, both
legally and physically, and its own processes for dealing with the
issues addressed in the Klamath Basin Restoration Agreement,” he said.
“The Trinity Settlement resolved issues between irrigators in the
Central Valley of California who divert water out of the
Trinity
Basin
into the
Central
Valley
, and the
tribes and Feds (and others).”
Q: Why not a proposal for additional water storage?
Could the lake be dredged to add storage? Could a deep-water reservoir
be added to the Basin?
A:
Oregon
State
Sen. Doug
Whitsett,
R-Klamath
Falls
, said
short water supplies in late summer are caused primarily by lack of
water storage in the
Upper
Klamath River
.
Compounding
the problem is earlier snowpack in the last few years. “The solution
is to develop new deep-water storage such as the proposed
Long
Lake
project,
the Boundary Reservoir, or any number of other smaller potential storage
locations,” he said. He doesn’t see dredging as a solution, he said,
because natural levels of bedrock-derived phosphorus would keep
releasing above-average levels of the element into the river and lake
system. Pablo Arroyave, area manager for the U.S. Bureau of
Reclamation’s Klamath Project, agreed. The Klamath Basin Restoration
Agreement commits the BOR to complete its current offstream storage
study by
Sept. 30, 2011
. Arroyave said the study is required before
BOR can get congressional authority to construct such a project.
Currently the off-stream storage study is looking at
Long
Lake
as
possible deep-water storage. He also didn’t see dredging as a solution
because the area that could be dredged would be unavailable to the
Klamath Project — below the lower level of the gates at the Link River
Dam — and the effort would just create “dead storage.” He added
that sediment disposal would present a very big problem. “For example,
adding just one acre-foot of storage capacity to the lake would lead to
more than 100 semi-truck loads of material that would need to be
disposed of — the lake holds about 485,000 acre-feet of water,” he
said.
Q: It seems that the agreement would settle some
adjudication, but not all? Where’s the line?
A: Ullman said the resolution of issues between the
Tribes and the Klamath Project is part of the agreement, but issues
between the on-Project and off-Project, as well as between the Tribes
and the off-Project parties haven’t been resolved.
That reflects the uncompromising stance of those
representing the off-Project in negotiations so far, he said, though
that is changing as the Tribes begin negotiating with individuals and
small groups that he said more accurately reflect off-Project interests.
The agreement allows future settlements and
resolutions to be incorporated. Ullman also said that participants in
the adjudication have the legal right to continue litigation if they
choose not to settle.
Bill Ganong, legal counsel for the Klamath Irrigation
District, said that to a large extent, the line is the north end of
Upper
Klamath Lake
.
The agreement, he said, frees all water users in the
Basin with a water right date of 1908 or earlier from the Tribal rights,
if any, in
Upper
Klamath Lake
and the
Klamath
River
. However,
he said those whose water right date falls after 1908 still have a
reason to contest Tribal claims. All people with water rights for
irrigation on the tributaries upstream of
Upper Klamath Lake
have a reason to contest the Tribal in-stream
claims in those tributaries. The agreement’s section 16 provides a
process and forum for resolving disputes across that line, Ganong said.
“The agreement encourages settlement by providing fair market value
compensation to landowners who agree to transfer part or all of their
water right in-stream,” he said. Many individual claims were resolved
by stipulated agreement, aside from Tribal claims, he said, others with
completed administrative hearing processes will be determined by a court
order.
“Following
entry of the adjudicator’s order each party will again weigh the
costs, risk and time that will be required by the court process against
the benefits, if any, of continuing the litigation,” Ganong said.
Q: What is the history of the power rates for on- and
off-Project users? What happened to make the rates jump up?
A: Addington said the Klamath Project enjoyed a
favorable power rate through contracts between Copco, PacifiCorp’s
predecessor, and Reclamation, first in 1917 and then in 1956. The 1956
contract renewal was required by the Federal Energy Regulatory
Commission (FERC) for Copco’s license and both contract and license
were to last 50 years. The irrigation rate agreement with the
off-Project also began in 1956. Both the agreements expired in 2006,
said Toby Freeman, regional community manager with PacifiCorp. Addington
said that since 2006, PacifiCorp operated under one-year licenses and
argued to FERC that the irrigator contract should not similarly be
renewed annually and FERC agreed.
Freeman said the Oregon Public Utilities Commission
ruled in 2006 that the off-Project should also move to the standard
irrigation rate and that no new contract was made because the special
rate for the Klamath irrigators wasn’t deemed to have a benefit for
all PacifiCorp customers.
The Public Utility Commission upheld that.
In the relicensing proceedings, Addington said, the
BOR submitted a condition to FERC that would require a new contract,
which is opposed by PacifiCorp and many others.
“Generally speaking, it is PacifiCorp’s view that
the old contract expired and is irrelevant, and there is no benefit to
PacifiCorp from the Klamath Project,” Addington said. “High power
rates would adversely affect water users and water use efficiency in the
Klamath Project.” (For more information about power from the KWUA,
visit its Web site, www.kwua.org/ power/power.htm.)
The current irrigation rates are rising to meet
standard irrigation rates, which are now at about 8 cents per kilowatt
hour in
Oregon
. Under the
1956 contract, the on-Project irrigators were paying 6.5 tenths of a
cent per kilowatt hour and off-Project users were paying 7.5 tenths of a
cent per kwh. Current tariffs in
Oregon
are $0.02
on and off project. On the
California
side,
tariff rates are $0.06 on the Klamath Project lands. The
Oregon
standard
rates are being phased in over a seven-year period, while the
California
rates will
be in place after only four years.
Q: Why not proceed with adjudication?
A: Ullman said adjudication creates winners and losers
based on priority date and quantified water rights. The winner-take-all
process doesn’t address the water availability problems, water
security, water quality problems, habitat problems, or timing of water
needs. “All these things must be dealt with if the current instability
for all communities is to be remedied,” he said.
The agreement also offers all involved a greater
degree of control than if the matter were turned over to a judge, Ullman
said.
Bill Ganong, Klamath Irrigation District’s legal
counsel, said even if irrigators were awarded their full water claims,
Tribal claims will have priority, which may limit irrigator use to nil.
“The Klamath Basin Restoration Agreement provides
specified amounts of water for irrigation in the Klamath Project that is
free of the Tribal claims, he said. “In addition, the agreement
provides financial compensation to irrigators who do not receive a full
supply of water.
“The benefits of the agreement outweigh the time,
cost and risk to Klamath Project Irrigators of continuing litigation in
the adjudication”
Litigation, he said, is expensive and inefficient. The
costs involved create large financial burdens for all involved.
“Many suits settle because one or more of the
parties cannot afford to continue the battle,” Ganong said. “The
costs of the
Klamath
River
adjudication to the state of
Oregon
, the
claimants and the contestants to this date is in the tens of millions of
dollars, and this litigation has not started the court process that
follows the pending administrative process.”
Adjudication has been pending for 30 years, and during
that time some land owners involved have simply gone out of business
because of money, retirement, job changes or death, he said.
Ganong expects that if the litigation route continues,
it will last many more years and few if any of the original irrigators
will be alive.
Claims are currently over the available water supply,
Ganong said, adding that each year, environmental regulations place more
limitations and demands on that shrinking supply. Climate change is
another monster looming in the future. In adjudication, the water supply
allocation and regulation will be determined by an adjudicator for the
Oregon Department of Water Resources scheduled for 2011, Ganong said.
With an order, the oldest rights will receive a full supply, while
younger water rights will probably get none during summer months. The
majority of water users will have to deal with whatever is available in
a given year, he said. No compensation will be awarded through
adjudication to those who get no water.
Q: Is there an estimate on what’s being spent on
adjudication by all parties, and would the settlement make all that go
away?
A: A hard and fast estimate of exactly what has been
spent by all parties involved in the adjudication litigation is not
available; however, Ganong guessed the figure to be in the tens of
millions.
The Klamath Project farmers have spent in excess of
$4.5 million, Ganong said, adding that he expected the U.S. had spent
much more and that the state of Oregon also had a huge investment as it
has paid most costs for the administrative hearing process and field
study of the irrigated land.
Ullman said the Tribes did not have a good estimate of
what has been spent on the adjudication, but did say the expense has
been “painful for all parties.”
Andréa Rabe, a Resource Conservancy board member and
off-Project rancher in the
Sprague
River
Valley
, said
adjudication expenses were in excess of $1 million in the off-Project.
Becky Hyde had heard $500,000, but that didn’t
include litigation expenses for off-Project landowners litigating Tribal
in-stream claims.
Hyde said farmers needed to seriously evaluate the
situation and “determine how deep your pockets are” and consider
what continued litigation means to the agricultural community
financially.
“What’s nice about this settlement is that there
is a choice — off-Project landowners who want to settle can, while
others who prefer to litigate these issues are welcome to,” she said.
Side Bar
'
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
NOTE: In accordance with Title 17 U.S.C. section 107, any copyrighted
material herein is distributed without profit or payment to those
who have
expressed a prior interest in receiving this information for
non-profit
research and educational purposes only. For more information go
to: http://www.law.cornell.edu/uscode/17/107.shtml
Source:
http://pioneer.olivesoftware.com/Daily/Skins/heraldandnews/navigator.asp?skin=heraldandnews
|