






|
Become a friend of
the Klamath Bucket
Brigade
Send
Donations Here
All donations are tax
deductible
|
|
This Website is Dedicated to
Alvin Alexander Cheyne
January
10, 1921 - June 17, 2005
|
|
|

Officials put side space for wetland projects
By STEVE
KADEL
H&N staff
writer
 |
|
Jenny Severson and Allison Cowie, land
specialists with Oregon Department of
Transportation, perform wetland delineation
Tuesday at a new bank of wetlands in
progress east of Olene on Highway 140. H&N
photo by Andrew Mariman |
OLENE — The Oregon Department of
Transportation is going into the banking business.
Banking of wetlands, that is.
The agency is expanding a wetlands area it
previously built adjacent to Highway 140 just east
of Olene. The purpose is to have wetland acreage in
the “bank” as a tradeoff for when road construction
projects fill parts of other existing wetlands.
“That way you have credits from the bank as you do
projects,” said Allison Cowie, wetlands specialist
for ODOT.
The federal Clean Water Act and the
state Removal-Fill Law require an acre-for-acre
trade so there is no net loss of wetlands, she said.
The current project will expand the Olene wetlands
from 4 1/2 acres to about 13 total acres.
Construction cost is $700,000.
Vegetation will be transferred from the Klamath
Wildlife Area on Miller Island to give it a good
start. Cowie said that’s cheaper and more effective
than using nursery stock.
“Nursery stock has less stored energy in its roots
because the roots are so small,” she said.
New concept
Cowie said banking is a relatively new concept in
wetlands mitigation. There are several banks in the
Willamette Valley, she said, but only a couple east
of the Cascade Range.
Some of the existing wetlands near Olene have
already served ODOT by mitigating the widening of
Highway 97 near Collier State Park.
Cowie said the agency plans to mitigate about five
road projects from the existing wetlands. The
larger, phase-two addition now under construction
will mitigate up to 20 road projects.
“Our impacts are generally very small,” Cowie said.
She explained that creating one large wetlands near
Olene would be more ecologically beneficial than
building two or three separate ones.
“When you create a really small wetlands, it doesn’t
create as many functions as a large wetlands,” she
said.
She said the existing wetlands near Olene have
thrived, so ODOT’s contractor is using the same
construction techniques. That includes building a
big bench with a berm separating the bench from the
Lost River.
The berm will allow plants to grow in the new
wetlands without being washed out by too much water,
Cowie said.
“We’ll create a kind of nursery for plants where we
can control the growth,” she said.
It will take the plants more than a year to become
stable enough to accept more water. Cowie said that
by October 2009 the berm would be removed “when the
plants are resilient to deeper water levels.”
Doing so earlier would drown the plants, she said.
Cowie added that it took about two years of meetings
and documentation to get the current project
approved.
Tom Feeley, ODOT construction project manager, said
the Olene project is using a couple of scrapers, an
excavator and trucks for hauling away dirt. The
material being removed will be placed nearer to
Highway 140, he said.
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
NOTE: In accordance with Title 17 U.S.C. section
107, any copyrighted
material herein is distributed without profit
or payment to those who have
expressed a prior interest in receiving this
information for non-profit
research and educational purposes only. For
more information go to:
http://www.law.cornell.edu/uscode/17/107.shtml
|