|
|
![]() |
| Ed Bartell |
The
worst-case scenario would be that a substantial water right is granted
to the Klamath Tribes or some other party. The Tribes or others could
then potentially shut down any irrigation that relies on surface water.
n For the Klamath Tribes:
A best-case scenario would be that they are granted a
substantial water right, allowing them to provide flows they view
necessary to fulfill hunting, fishing and gathering needs provided by
treaty rights.
Worst-case scenario would involve the Tribes not being
granted enough water to ensure the flows and lake levels they view
necessary, specifically for restoring their threatened and lost
fisheries.
What
about the agreement?
The
proposed Klamath Basin Restoration Agreement wouldn’t end the
adjudication process, but it could make it shorter and less costly for
on-Project irrigators and Tribes as water rights are more clearly
defined. In the agreement, on-Project irrigators agree to limit their
use of
The
state of
But
pressure is building to move the process along.
Pros
and cons?
The Tribes benefit from the agreement by knowing that some level of
water will be in the lake, contributing to restoration efforts. Both
Tribes and irrigators benefit from diminished conflict and litigation.
“This is by far the best solution,” says Bud
Ullman, tribal attorney.
But others criticize the agreement, saying it
doesn’t provide the protections that proponents say it does. n Ed
Bartell, president of the off-Project Water Users, says the Tribes will
still be able to take water from the Project because they do not
surrender their sovereign nation rights in the agreement.
![]() |
| Dave Solem |
Ganong,
Ullman and Dave Solem, Klamath Irrigation District manager, say that it
would be difficult for future tribal leaders to overrule a legal
contract. The Tribes do not want to end agriculture in the Basin and
leaders from both sides want to foster a better relationship.
“We would not settle if the Tribes could come back
and say the deal’s off,” Solem says.
n Bartell also says that off-Project irrigators (those
irrigators whose land is not within the Reclamation Project’s borders)
will still have to go through the adjudication process with no certainty
of an outcome.
Ullman says that the off-Project irrigators had the
same opportunity to negotiate with the Tribes as those on the Project.
![]() |
| Doug Whitsett |
n
State Sen. Doug Whitsett, R-Klamath Falls, criticized the agreement
before it was even released, saying his sources indicated that it would
not comply with Oregon water law, among other issues.
But Ochoa says one of the reasons the state supports
the settlement agreement is because it complies with
![]() |
| Bud Ullman |
What’s
been done?
Water
adjudication has been a drawn out process in the
In
the early 1990s, the state began to request more claims and challenges,
and 1996-1997 was the last period they were accepted. In all, 730 claims
and 5,664 challenges were filed; only 24 claims went unchallenged.
Ganong
says on-Project irrigators have spent an estimated $4.2 million on water
adjudication to date. That money paid legal and court fees, travel, and
the costs of services needed to support on-Project claims.
For
example, historians were hired by irrigation districts to research and
find water rights documentation. Others were hired to make extensive
maps to demonstrate and verify claims.
In
all, Klamath Irrigation District filed 10,000 pages of forms with their
claims, along with another 10,000 pages of supporting documentation.
![]() |
| Greg Addington |
What’s
next?
A
decade later, the state’s role in the adjudication is nearing
completion. Nearly all the claims and challenges are settled
administratively; the remaining 56 claims and 201 challenges pertain to
the Tribes. Of the claims and challenges already settled, Greg
Addington, executive director of Klamath Water Users Association, said
they haven’t gone in favor of one side or another.
As opponents and proponents debate the proposed
Klamath Basin Restoration Agreement, the state has suspended
adjudication to provide time for those affected to consider their
options, but they only have so long.
Water Resources requested an extension of the
suspension until April 4 but officials say they will not make any
further requests.
Ochoa says the department is eager to move the process
forward because the Legislature set aside money for the process during
the 2007 regular session and wants to honor that decision. The
department also believes that two months should be sufficient to reach a
decision on the agreement. If a decision isn’t reached or if the
settlement is scrapped, adjudication would continue as scheduled,
leaving the future of on-Project irrigation in the hands of attorneys
and judges.
Ganong says that without the settlement, the water
adjudication process could drag on for three-quarters of a century or
more.
Costs would rack up as on-Project irrigators would
need to continue to challenge evidence produced against their claims.
Water has become an increasingly valuable resource and
without negotiation, the conflicts over it will not end soon. “It’s
become worth fighting over,” Ganong says.
What
else?
n The Klamath Basin isn’t the first to go through
the process. Basins such as
n Other claims and challenges are pending above Upper
Klamath Lake involving the Tribes and there would still be some
administrative proceedings as the agreement would function as a
recommendation to the adjudicator, not a final order. Off-Project water
users also have a challenge filed against on-Project irrigators.
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
NOTE: In accordance with Title 17 U.S.C. section 107, any copyrighted
material herein is distributed without profit or payment to those
who have
expressed a prior interest in receiving this information for
non-profit
research and educational purposes only. For more information go
to: http://www.law.cornell.edu/uscode/17/107.shtml
Source: http://pioneer.olivesoftware.com/Daily/Skins/heraldandnews/