IN THE UNITED STATES COURT OF FEDERAL CLAIMS
KLAMATH
IRRIGATION DISTRICT et al.,
)
)
Plaintiffs,
)
)
No. 01-591L
v.
)
)
Judge Diane Gilbert Sypolt
)
Defendant.
)
__________________________________________)
(CORRECTED)
SUPPLEMENTAL JOINT PRELIMINARY STATUS REPORT
The parties file this Supplemental Joint
Preliminary Status Report (JPSR) addressing plaintiffs’ breach of contract
claims, as agreed in the Joint Proposed Schedule for Further Proceedings on
the Breach of Contract Claims filed by the parties filed
a. Jurisdiction
Plaintiffs’
statement. This Court has jurisdiction over this case under
28 U.S.C. §
1491 (the Tucker Act) as a “claim against the
Individual plaintiffs, Fred A. Robison, Albert J.
Robison, Lonny E. Baley, Mark R. Trotman, Baley Trotman Farms, James L. Moore,
Cheryl L. Moore, Daniel G. Chin, Deloris D. Chin, Wong Potatoes, Inc., Michael
J. Byrne, Daniel W. Byrne, and Byrne Brothers assert their claims as third
party beneficiaries of those contracts, as they are the actual users of the
Klamath Project water delivered under those contracts, and have paid to
Reclamation all sums due thereunder.
Plaintiffs request that any challenge to this Court’s jurisdiction to
hear their claims as third party beneficiaries be resolved by motion at the
Court’s earliest convenience in the interest of judicial efficiency and the
economies of the parties.
Defendant’s statement.
At this preliminary stage of
the case, Defendant does not dispute that the Court has jurisdiction over the
claims of the plaintiff irrigation districts that have contracts with
Reclamation. However, because
Klamath Hills District Improvement Company does not have a contract with
Reclamation for delivery of Project water, this Court may lack jurisdiction
over its claim. In addition,
because the named individual plaintiffs’ status as intended third party
beneficiaries of these contracts has not yet been established, Defendant
submits that the Court may lack jurisdiction over their claims.
To the extent that Plaintiffs suggest that the payment of money under
the contracts is relevant to the question of whether Reclamation has breached
its contracts with the irrigation district plaintiffs in this case, Defendant
submits that the issue may be in dispute.
b. Consolidation.
The
parties are unaware of any other case with which this case should be
consolidated.
c. Bifurcation.
The parties agree that
the case should be bifurcated, with liability being decided first.
As noted below, the parties further agree that liability should be
resolved on summary judgment.
Plaintiffs’ statement: Since
this Court has before it all of the signatories to the contracts, plaintiffs
respectfully suggest that the issue of liability—i.e., was defendant’s
failure to deliver water in 2001 a breach of those contracts—be resolved
independently of class certification.
Since an adverse determination on third-party beneficiary standing (see
Section 1 above) or on liability would moot the class certification issue, and
since class certification is significant only to damages in this case,
plaintiffs respectfully suggest that the motion for class certification as to
the contract claim be deferred until after liability has been determined.
Defendant’s statement: Defendant
requests that the Court first resolve the class certification, representative
capacity, and third party beneficiary issues with respect to the breach of
contract claims. Plaintiffs
have not filed a motion for class certification which specifically addresses
their breach of contract claims, but if plaintiffs plan to proceed in this
capacity, defendant submits that plaintiffs should file such a motion.
Defendant further notes that a determination of whether a class should
be certified should be made in advance of any determination of liability.
See RCFC 23(c) (1) (“[a]s soon as practicable after the commencement
of the action brought as a class action, the court shall determine by order
whether it is to be so maintained.”). Once
plaintiffs have set forth the basis upon which they assert the appropriateness
of class certification, or the basis of their alleged representative or third
party beneficiary status, defendant will likely seek to conduct discovery
before filing a response. See
Defendant’s Response to Plaintiffs’ Supplemental Filing (
d. Deferral of further proceedings. The parties are unaware of any reason to defer the
breach of contract claims in this case based on other pending cases in this
Court or any other tribunal. The
parties are unaware of any basis for transferring this case to another
tribunal, or of any related case pending in another tribunal.
e.
Remand or suspension.
The parties agree that no remand or suspension will be
sought in this
case.
f.
Additional parties.
The existing parties do not intend to join any other parties
at this time.
g.
Dispositive motions. The
parties anticipate that liability can be resolved on summary judgment pursuant
to Rule 56, following a nine-month discovery period.
Plaintiffs’
statement: As
noted above in Sections A and B, plaintiffs suggest that any RCFC 12(b)(1)
motion to dismiss which defendant may choose to file, challenging the
jurisdiction of this Court, should be filed at the earliest possible time to
avoid unnecessary waste of the Court’s and the parties’ resources.
Defendant’s
statement: It is
possible that defendant may file a RCFC 12(b)(1) motion seeking dismissal of
certain plaintiffs after a period of discovery should the parties be unable to
resolve the class certification and representational capacity issues with
respect to plaintiffs’ breach of contract claims through informal discussions
or through a motion by plaintiffs seeking class certification or setting forth
the basis for their representational or third-party beneficiary standing.
Specifically, defendant may seek to dismiss the named individual
plaintiffs should plaintiffs fail to establish their status as intended third
party beneficiaries of the irrigation district plaintiff contracts with
Reclamation. In addition, to the
extent that plaintiff Klamath Hills District Improvement Company is asserting a
breach of contract claim, defendant may seek to dismiss that claim because
Klamath Hills District Improvement Company does not have a contract with
Reclamation.
The
parties anticipate filing motions for summary judgment pursuant to RCFC 56 on
the question of liability for the breach of contract claims following a
nine-month period of discovery. At
this preliminary stage, defendant has several potential grounds for a
dispositive motion, including:
1.
A majority of the irrigation district contracts with Reclamation contain
water shortage provisions that limit the liability of the
2.
The contracts generally do not specify particular quantities of water to
be delivered by Reclamation.
3.
Under existing law, Reclamation is not liable to the plaintiffs for a
reduction of water deliveries if those reductions are necessary to comply with
legal obligations. See Klamath
Water Users Assoc. v. Patterson, 204 F.3d 1206, 1212-14, opinion amended
on denial of rehearing, 203 F.3d 1175 (9th Cir. 2000), cert. denied,
531 U.S. 812 (2000); O’Neill v. United States, 50 F.3d 677, 689 (9th
Cir. 1995), cert. denied, 516 U.S. 1028 (1995); Kandra v. United
States, 145 F. Supp. 2d 1192, 1199 (D. Ore. 2001).
h.
Relevant Factual and Legal Issues.
At this point the parties have not identified any material disputed factual issues concerning liability. Specifically, the parties agree that:
1.
The irrigation district plaintiffs, with the exception of Klamath Hills
District
Improvement
Company, have contracts with Reclamation for the delivery of Project water.
The
parties have identified the following legal issues for resolution by this Court:
1.
What is the scope and extent of Reclamation’s contractual obligations?
2.
Whether Reclamation breached its contracts with the irrigation districts.
3.
If there has been a breach, what measure of damages is owed to
plaintiffs.
Plaintiffs’ statement. Reclamation
does not deliver water directly to Klamath Project water users.
Instead, it has entered into a series of contracts with plaintiff
districts to accomplish that water delivery.
Although the contracts vary somewhat in their precise terms, the
contracts generally obligate Reclamation to deliver (subject to availability)
all water that the Klamath Project water users can beneficially use on their
land. As consideration for these
water deliveries, the districts are obligated to pay Reclamation annually the
entire cost of water storage and delivery. Moreover,
the districts have completed their payment to Reclamation of the entire capital
cost of Klamath Project facilities, such as the dam, irrigation canals, tunnels,
and pumps.
Prior to 2001, with minor exceptions in 1992 and 1994 (critically dry
years), Reclamation had faithfully made these water deliveries to plaintiffs
every year. In 2001, Reclamation
again proposed to deliver water in accordance with historical practice.
Reclamation’s operations plan for 2001, however, was found to
jeopardize the endangered fish (suckers and salmon) in the government’s
The Supreme Court construed similar Reclamation water delivery contracts
in Ickes v. Fox, 300 U.S. 82 (1937) holding that Reclamation could not
unilaterally decrease its water deliveries to project water users, nor raise the
price. The Court noted that “[t]he
government was and remained simply a carrier and distributor of the water, with
the right to receive the sums stipulated in the contracts as reimbursement for
the cost of construction and annual charges for operation and maintenance of the
works.” The Court ruled that
twenty years of contract performance established Reclamation’s interpretation
of the contract—that plaintiffs are entitled to delivery of all the water they
can beneficially use, subject only to availability.
The Comptroller General, noted that the Klamath contracts are
substantially similar to those at issue in Ickes.
Dec. of Comptroller General, No. B-125866, 1956
Plaintiffs do not believe that the limitation of liability provision
(which also differs from contract to contract, and which is entirely absent from
some) bars recovery of breach damages where Upper Klamath Lake was full, and
plenty of water was therefore available for delivery.
Moreover, to the extent that an Act of Congress makes contract
performance illegal, the defense of supervening illegality is unavailable to
defendant. United
States v. Winstar Corp., 518 U.S.
839, 883 (1996) (“[W]e must reject the suggestion that the Government
may simply shift costs of legislation onto its contractual partners who are
adversely affected by the change in the law, when the Government has assumed the
risk of such change.”).
As noted above, once liability is found, this Court
will have to determine the proper measure of damages.
Plaintiffs believe this measure of damages is the consequential damage
caused to the 1400 water users, while defendant has not yet come to a position
on this issue. Accordingly, at the
time liability has been found, this Court may be required to determine whether
the individual water users, individually or as a class, are necessary parties to
this suit, or whether the district plaintiffs may recover their losses as a
proper measure of damages without certifying the class.
Finally, plaintiffs are aware that a few individual Klamath Project water
users have indicated their intention to seek damages in another forum, and
plaintiffs have assured defendant that they will not assert any damages claim on
behalf of those individuals.
Defendant’s statement.
A. Factual Background
Defendant
incorporates by reference its statement of the Factual Background contained in
the Joint Preliminary Status Report filed on
The
delivery of Project water is governed by contracts entered into between
Reclamation and various individuals, irrigation districts and other entities
organized under Oregon and California law (collectively referred to herein as
the “Districts”). See
Klamath Project Historic Operation at 31-32, C-1 - C-2 (“The Klamath Project
water users obtain their irrigation water supply from Project facilities
pursuant to various contracts with Reclamation.”).[1]
Each of the districts then supplies irrigation water to individual users
within their boundaries. All but one
of the irrigation districts named as Plaintiffs in this case have contracts
directly with Reclamation for the delivery of Project water.
See Pls’ Amended Complaint Exs. 1-14.
Klamath Hills District Improvement Company does not have a contract with
the
The
contracts at issue are written in perpetuity, generally specify an acreage for
which water is to be provided, and rely on beneficial use for the amount of
water used rather than specifying an amount of water to be delivered.
In addition, many of the contracts provide that the water is to be
delivered during the irrigation season, generally defined as a period between
April and September. To
the extent that Plaintiffs suggest that the payment of money under the contracts
is relevant to the question of whether Reclamation has breached its contracts
with the irrigation district plaintiffs in this case, Defendant submits that the
issue may be in dispute. A
majority of the contracts also contain water shortage provisions which limit the
liability of the
B.
Legal Issues
Defendant
incorporates by reference the Legal Issues contained in the Joint Preliminary
Status Report filed on February 8, 2002 at 18-19 and further states that at this
early stage in the litigation, Defendant views issues 5, 6, and 7 from p. 19 of
the JPSR filed on February 8, 2002 as potential issues of law with respect to
Plaintiffs’ breach of contract claims. As
set forth in the
5.
Whether Plaintiffs have stated a claim for which relief can be granted.
6.
Whether the Plaintiffs’ contracts with the Bureau of Reclamation
preclude liability against the
7.
Whether Plaintiffs’ contract rights are contingent upon Defendant
meeting the requirements of the ESA and its trust responsibility to Indian
tribes.
Defendant
disputes plaintiffs’ reliance on the case of Ickes v. Fox, 300 U.S. 82
(1937). That case involved a different Reclamation project and different
Reclamation contracts. In
addition, Defendant believes that many of the factual contentions contained in
Plaintiffs’ statement are disputed and also disagrees with Plaintiffs’
interpretation of the other cases and documents relied on in their statement.
In addition, Defendant views the following as additional issues with
respect to the breach of contract claims:
1.
Whether the irrigation district plaintiffs may bring their claims in a
representative capacity, and if so, what is the scope of that capacity.
2.
Whether the named individual plaintiffs are third party beneficiaries of the
irrigation district plaintiffs’ contracts with Reclamation.
3.
Whether this case should proceed as a class action and, if so, how should the
class be defined, who are the proper class representatives, and should there be
any subclasses.
The
parties have been in discussions regarding the question of who the proper
parties are to assert plaintiffs’ breach of contract claims, and how and when
these questions should be resolved. Thus
far, the parties have been unable to resolve this issue.
While Defendant agrees that the irrigation district plaintiffs who are
parties to contracts with Reclamation may bring the breach of contract claims
set forth in Plaintiffs’ amended complaint, it is far from clear whether these
irrigation district plaintiffs may bring their breach of contract claims on
behalf of the water users within their districts or whether the individual
plaintiffs may bring claims on their own behalf as intended third party
beneficiaries. For example,
Plaintiffs have not demonstrated that the state statutes which purport to
authorize the irrigation districts to maintain actions afford them
representational standing to bring breach of contract claims.
Moreover, the case cited by Plaintiffs, H.F. Allen Orchards v. United
States, 749 F.2d 1571 (Fed. Cir. 1984), does not support plaintiffs’
alleged intended third-party beneficiary status.
See Joint Report Responding to Court’s Order of
Defendant
also believes that it may be necessary to conduct some discovery relating to the
class certification/representative capacity issue.
Defendant would anticipate seeking information from Plaintiffs regarding
whether any of the named irrigation districts have a charter, articles of
incorporation or similar documents that define each district’s purpose and
powers, whether written agreements/contracts or other evidence exist that define
the relationship between each of the irrigation districts and the individual
landowners and water users within that district, and whether the water users
within each district have specifically authorized the districts to file claims
on their behalf and whether that authorization is documented.
Defendant
has also been notified that certain water users that receive water from the
named irrigation district plaintiffs have not elected to pursue breach of
contract claims through this lawsuit. Therefore,
Defendant seeks a resolution of this issue that takes into account the fact that
not all water users within each district wish to be part of this lawsuit.
i.
Settlement/Alternative Dispute Resolution.
The
parties have discussed whether any method of alternative dispute resolution may
be viable to address the breach of contract claims in this case.
At this preliminary stage of the case, the parties do not believe any of
these methods are viable because the parties believe the question of liability
on the breach of contract claims can be resolved through motions for summary
judgment.
j.
Anticipate Proceeding to Trial/Expedited Trial. At
this time, the parties do not believe that a trial to determine the liability
issue will be necessary. As this
time, neither party requests expedited trial scheduling.
k.
Electronic Case Management.
At this time, there are no special issues regarding electronic case
management needs.
l.
Other information for the Court.
Counsel represent that the parties discussed the issues set forth in
Paragraph 3 of Appendix A of the Rules of the Court of Federal Claims on
Plaintiffs’
counsel certifies that he has discussed the expenses and time frame for this
litigation with his clients. Defendant
certifies that it has discussed time frame and litigation costs with the client
agencies involved in this case. Both
parties agree that there are many variables, which may affect the timing and
costs for the conduct of this case, and have discussed such variables with their
clients.
m.
Discovery Plan.
The parties agree that a nine-month period will be necessary to complete
discovery that is limited to the question of liability on the breach of contract
claims. Moreover, the parties
further agree to conduct discovery on the issues of liability and proper party
issues (class certification/representative capacity) simultaneously.
The parties propose the following discovery schedule:
1. Initial Discovery Period
on Proper Party Issue will close on
2. Discovery on Liability
will close on
With respect to Part 6 of this Court’s Special Procedures Order, the
parties respectfully refer the court to the Revised Appendix to the Joint
Preliminary Status Report filed with the Court on
Plaintiffs’ statement. As noted above, plaintiffs believe that the district plaintiffs have standing to assert all breach of contract and damages claims on behalf of their water users. However, in order to afford complete relief and to assure that all parties are before the Court, some individual plaintiffs are also named, suing on their own behalf and on behalf of the class of all Klamath Project water users.
Plaintiffs respectfully suggest that the standing of individual plaintiffs (as well as all similarly situated individual water users) is properly tested by a RCFC 12 (b)(1) motion, which defendant should file at the earliest opportunity. This Court’s ruling on that motion may moot class action certification, making the motion to certify superfluous. For example, should this Court hold either that the district plaintiffs have the right to recover damages for their water users, or should this Court hold that individual water users are not third party beneficiaries, class certification would be moot.
Since jurisdictional issues are generally addressed at the outset of the
case, and since class certification motions are often deferred to a later point
in the litigation, plaintiffs suggest that defendant’s RCFC 12(b)(1) motion
should proceed a class certification motion with all of its panoply of factors
and inquiries in addition to standing issues.
Accordingly, plaintiffs recommend that this Court order defendant to file
any RCFC 12(b)(1) motion it may have on or before
Defendant’s statement. If the parties are unable to reach agreement on the issue of class certification and representative capacity with respect to the breach of contract claims, defendant reiterates its request, as set forth in its Response to Plaintiffs’ Supplemental Filing (April 10, 2003), that plaintiffs be required to file an amended or supplemental motion for class certification that includes the basis for class certification of the breach of contract claims under RCFC 23. Defendant further requests that once plaintiffs have set forth the basis upon which they assert the appropriateness of class certification or the basis of their alleged representative capacity, that defendant be allowed 90 days to conduct discovery on the issue of class certification/representative capacity. Defendant requests that it have 30 days from the close of discovery on these issues within which to file its Response to Plaintiffs’ motion. Because plaintiffs have yet to specify or establish in which capacity they bring their breach of contract claims, Defendant submits that plaintiffs’ motion should address these issues before Defendant files a RCFC 12(b)(1) motion. As set forth above, this issue should be resolved prior to the issue of liability with respect to the breach of contract claims.
Defendant
additionally proposes the following schedule:
1.
Plaintiffs to file Motion for Class Certification
2.
Defendant to File Response to Motion for Class Cert.
Respectfully
submitted,
________________________
Roger
J. Marzulla
Nancie
G. Marzulla
Marzulla
& Marzulla
Tel:
(202) 822-6760
Fax:
(202) 822-6774
Counsel
for Plaintiffs
THOMAS
L. SANSONETTI
Assistant
Attorney General
Environment
& Natural Resources Division
________________________
KRISTINE
S. TARDIFF
Attorney
of Record for Defendant
JOANNA
B. GOGER
United
States Department of Justice
Environment
& Natural Resources Division
General
Litigation Section
Ben
Franklin Station
Tel:
(202) 305-0481
Fax:
(202) 305-0506
REGINALD
T. BLADES, JR.
Senior
Trial Counsel
Commercial
Litigation Branch
Civil
Division
Department
of Justice
Attn:
Classification Unit
8th
Floor,
Tel:
(202) 514-7300
Fax: (202) 307-0972
Dated:
[1]
This document is available at http:www.usbr.gov/mp/kbao/docs/Historic%20Operation.pdf.
[2] The parties agree that if the proper parties question is not resolved during this discovery period, an additional period of discovery may be required by one or both parties after resolution of that question.