
The Klamath Project
The Klamath
Project encompasses an alternately barren and wooded area of
Project Location
The Klamath
Project covers territory in
Historic Setting
Settlers
carved their niche in
To
protect the
I'm a raw recruit with a brand new suit.
One hundred dollars bounty.
And I've just come down to
To fight for
The
First Oregon paid the cavalry troopers $31 to $39 a month. Sergeants received a
few dollars more.
Looking
for a strategic location to secure major migration routes, the Regiment's
officers chose the
Five
years later conflicts between the Klamath and Modoc Indians, placed on the same
lands by the United States Government, resulted in the Modoc War. Kientpoos,
more commonly known as Captain Jack, led the Modocs to
In 1882, five
years after the Modoc War, farmers introduced irrigation to the Klamath area.
Several Linkville residents incorporated the Linkville Water Ditch Company. They
dug a low capacity ditch connecting town lots to the
The Van Brimmer
Brothers also started a small ditch in 1882, to irrigate 4,000 acres near the
Oregon-California border on
Project Authorization
In
October 1903, John T. Whistler, Oregon District Engineer of the Reclamation
Service, investigated the Klamath region at the request of Chief Engineer, later
Reclamation Director, Fredrick H. Newell. Whistler recommended a controlling dam
at the lower end of
Approval
of the Klamath Project rested on adjudication of all vested and conflicting
water rights; surrender of rights on Lower Klamath and Tule Lakes; cessation of
rights and title to the federal government by Oregon and California for Lower
Klamath and Tule Lakes; and Congressional approval allowing Hitchcock to destroy
navigability of the two lakes. Hitchcock and Newell received petitions for a
Reclamation project beginning in late 1904 and early 1905, as residents of
Only
the Klamath Canal Company threatened project authorization. Three men named
Hawkins, Brown, and Gould incorporated the Klamath Canal Co. on
Reclamation
filed on the waters of
The
Justice Department responded by issuing a temporary restraining order. Meanwhile
land owners in the
Local
farmers unanimously supported the project and organized the Klamath Water Users'
Association on
Construction History
The
Klamath Project incorporated several privately built canals and, Reclamation
initially constructed Clear Lake Dam and Reservoir, Lost River Diversion Dam,
and the A (Main), B (East Branch), and C (South Branch) Canals on the Project.
The
Construction
of the Klamath Project started under the direction of Project Engineer D. W..
Murphy in 1906, and continued under Walter W. Patch, his 1909, replacement.
Mason, Davis & Company of
Mason,
Davis & Co. could not work on three miles of the
The
rain and snow, of winter, made canal excavation a slow and arduous task. The
work required three steam pumps to handle water from the canal. Mason and Davis
could only use the horse teams on the upper portions of the canal cut. The
company received a contract extension and completed two sections of the canal
Reclamation
invited bids for construction of the
Original
plans intended the
Another
board of engineers, consisting of Henny, Hopson, and Murphy, convened in
The
plan went awry as only one company bid on the schedules. Reclamation considered
the bid excessive and decided to proceed by force account for the entire canal.
Work started in June 1907. Excavation work promptly ran into unexpected
dilemmas. The hillside slopes of the canal location proved very steep, with
houses and orchards immediately below the site, and a power plant and wooden
pressure pipe nearby, on the
The
Project History complained of having scarce and unsatisfactory laborers,
whom Reclamation paid $3.00 for an eight hour day, for several months.
Reclamation finished the canal excavation in October 1908. Upon priming the
canal, Reclamation discovered considerable seepage which caused movement of the
lower banks. Reclamation lined the right bank and bottom of the canal, with four
inches of concrete, for a distance of 267 feet. Workers placed riprap the same
distance along the left bank. The lining and riprap reduced the seepage greatly,
but Reclamation maintained a force of three to five men for several months to
puddle subsequent seepage with soil and manure.
Reclamation
awarded the contract for three schedules of the South Branch Canal to Maney
Brothers of Saint Louis on May 8, 1908, and they began work five days later.
Maney Brothers did all the excavation work with horses and scrapers. Reclamation
allowed a contract extension from
The
W.
H. Mason of
J.
M. Heizer conducted studies of the proposed
Reclamation
placed William Sargeant in charge of dam construction. In April 1909, he
supervised building of the construction camp, organizing the work, and receiving
equipment and supplies. Austrians, Montenegrins, and Serbians formed the
majority of the work force. Reportedly the Austrians proved outstanding workers,
though supervisors considered all satisfactory. Reclamation bought $10,000 worth
of new equipment for construction, and had to haul the new equipment fifty-five
miles, from the railroad to the dam site. The Reclamation Service increased the
labor force in June to begin work on the waste channel. Workers used material
excavated from the waste channel in the rockfill portion of the dam.
The
outlet conduit from the dam to the waste channel stretched 156 feet when
completed. The outlet started as two chambers near the foot of the dam,
controlled by cast iron gates. The chambers joined forty feet below the gates,
forming the main conduit. Workers excavated an average of eighteen feet deep.
They encountered porous lava covering hard basalt ten feet deep. Under the
basalt they found "a sticky, red, volcanic mud." The crews excavated
cutoff trenches through the muck to the hard rock three feet below and filled
them with concrete to stabilize the foundation. The conduit is ten feet in
diameter.
Reclamation
used levees built by Jesse Carr to divert Willow Creek into
Workers
used material excavated from the waste channel for the rockfill. The arrangement
limited the placement rate on the fill to the excavation rate of the channel.
Reclamation built
Reclamation
crews dug through two feet of tule and marsh grass across the channel to the
foundation of the earth embankment. After draining water from the site, the
ground surface became impenetrable to the orange-peel excavator acquired for
clearing the site. Workers used a plow on the hard material. The material
immediately beneath the surface proved too soft to support loaded wagons.
Workers rigged up a hoisting engine at one end of the site, attached a plow and
slip to it with a cable, and used the combination to excavate the soft material.
Seven
feet below the surface lay solid basalt slabs with only a few seams. Crews
washed the rock, then cleaned the cracks with wire and grouted them. Work crews
discovered lava blocks separated by clay seams forming the foundation on the
east side of the river. They used gads, steel wedges used to break out loose
pieces of rock, and bar drills, small rock drills, to excavate the trench
between the lava boulders, afterwards filling the seams with grout or cement,
depending on the size of the cracks. On the west side, porous lava seams
permeated the foundation. Workers excavated through the lava to the solid rock
below. They filled the excavated portions with concrete. A four ton, cast iron
roller leveled and compressed the re-fill to four inch layers.
Crews
filled gaps in the rockfill at the contact point with the earth embankment for a
proper foundation. They placed the earth, taken from the east slope of the
valley, in six inch layers, watered it, and compressed it with a four ton
roller. A nearby borrow pit supplied the stones for the riprap on the upstream
slope.
Lava
encountered in excavation of the waste channel varied in hardness, causing
problems for Reclamation crews. They used 40 percent dynamite to
"spring" drill holes, then finished blasting with 50 to 500 pounds of
"Champion" powder. Where water in the excavation site prevented the
use of powder, the crews used only the dynamite. Uncertainty of the rock's
density often resulted in charges being too light or too heavy. Explosions from
light charges dissipated through seams and soft spots. Heavy charges dislodged
more material than desired. The resulting excavated material ranged from
powdered rock to boulders. The boulders required block-holing, or drilling holes
in the rocks for a small charge of explosives to break them for removal.
Labor
shortages afflicted construction of
Reclamation
identified two saddles to the south of
The
labor shortages at
Reclamation
intended to build
President
William Howard Taft authorized the issuance of bonds against the Reclamation
Fund in 1910, for future work on projects including the Klamath Project. Before
expenditure of money from the bonds, he ordered a Board of Engineers from the
Army Corps of Engineers examine and report on each project using the bonds. The
Board of Engineers visited the Klamath Project September 30 through
Reclamation
engineers decided, in 1910, to put Lost River Diversion Dam at a site called
Though
it still required some finishing work, Reclamation began storing water behind
the Lost River Dam in January 1912. The gatekeeper and a small work force
applied the final touches. They built two wing walls at the downstream end of
the dam, a garage near the dam, and completed other smaller projects. The Lost
River Diversion Dam is a hollow U shaped multiple arch weir, with straight
embankment wings. The dam's crest length extends 675 feet with a structural
height of 42 feet.
W.
H. Mason of
Mason
waited for the arrival of an excavator to continue canal excavation. The machine
arrived in June 1911, but a poor design limited its effectiveness. After moving
only 2,000 cubic yards, Mason discarded the excavator in favor of team work.
Mason lost valuable time, and Reclamation lost patience. In September 1911
Reclamation suspended the contract schedules contract not yet started by Mason,
and completed them by force account, finishing
James
Jory contracted one schedule on the diversion channel and began in May 1911.
Jory started with a small force and repeatedly experienced delays. He made
little headway by the end of the year. By March 1912, Jory realized he faced
penalties if work did not make the deadline. Jory pushed his work through
continuing winter conditions and financial losses, completing the contract on
Construction
remained light for the next several years. Reclamation built a sixty-four foot
truss span by force account, in 1912, to extend the
Reclamation
received authorization to excavate the
Reclamation
finished the
Reclamation
drew up plans for the
Reclamation
reached an agreement on
Payne
listened to arguments and explanations about the contract in a hearing on
Construction
of the Lower Lost River Diversion Dam coincided with construction of the J
Canal, to supply water to the Tule Lake Division. W. D.. Miller of
Excavation
of J Canal by force account began
Reclamation
built Malone Diversion Dam, on the upper
Lava
bedrock comprised the foundation on the south side of the river bed. On the
north side lay lava boulders and gravel mixed with clay, ash, and cinders. A
"black mucky material," of decomposing vegetation, covered the bed to
a depth of about six feet. Workers removed the material with a stiff leg derrick
down to the foundation material. Slip scrapers and laborers' hands took care of
the rest. Reclamation started placing the earthen embankment
Concrete
placement started
Reclamation
experienced labor shortages in the 1920s, as it had in previous years on the
project. The Service experienced a high turnover rate during construction of
Malone Dam. Common labor received between $3.60 and $4.50 a day. Reclamation
paid carpenters $7.00 a day on the dam construction. Wages in the surrounding
area reached $4.00 to $5.00 a day for common labor. Malone Diversion Dam
consists of a concrete gate structure with a height of 32 feet, and a crest
length stretching 515 feet.
Reclamation
opened bids for twelve miles of the
W.
E. McAboy received a contract to build the checks and wasteway structures on the
W.
D. Miller received the contract to build the Gerber Dam, located on Miller
Creek; formerly the Horsefly site, on
Gerber
Dam is a concrete medium thick arch, 460 feet long at its crest. The dam stands
eighty four and one-half feet high with a top width of five feet and a maximum
base width of twenty-four feet. The spillway consists of an uncontrolled
overflow section at the dam's center. Water first spilled in 1958. Gerber
Reservoir has a total capacity of 94,300 acre-feet.
Reclamation
built the
New
construction on the Tule Lake Division began in 1940 with the creation of the
Modoc Unit of the division. Reclamation started excavation on the P and P-1
Canals
Reclamation
awarded the contract for the Tule Lake Tunnel to J. A. Terteling & Sons. The
tunnel drained water from the
Terteling
lined the tunnel with a layer of concrete, measuring a maximum of seven inches
and minimum three inches thick. Workers used a pumpcrete machine to inject the
concrete into the tunnel forms. Terteling's concreting equipment often failed,
due to its age, but the company finished the work on
John
Gardner of
In
the early 1940s, Reclamation instituted plans to convert lands reclaimed from
the
Post-Construction History
Squirrels
caused major problems for the Klamath Project early in its history. Squirrel
holes in canal embankments caused eleven of twelve breaks in A and C Canals in
1915. Fortunately only three breaks proved serious; two in A Canal and one in C
Canal. Reclamation officials deemed the original timber lining in C Canal unsafe
in 1919. Reclamation re-lined the canal with concrete starting in fall of 1919,
and continuing into 1920. During freezing weather, workers covered the concrete
work with canvas and heated it with fires to prevent damage. Working from
Once
again labor shortages hindered Reclamation's progress. Regulations limited the
maximum wage paid by Reclamation to $4.50 per day. Elsewhere employers paid
laborers $5.00. Reclamation received the authority to pay $5.00 per day, and by
the end of 1920, workers on C Canal received $5.50-$6.00 per day. Carpenters
received $8.00 per day. Reclamation now deducted $.50 per meal from the workers'
pay. Wages continued to fluctuate in 1921 and 1922. Wages dropped to $3.60 per
day in 1921, and fell to $3.00-$3.20 in early 1922. Common laborers' pay rose to
$4.00 per day on
Reclamation
advanced from simply lining C Canal to enlarging it. Work crews used an
excavator on softer material, but they encountered a layer of hardpan strata
requiring heavy blasting. The Oregon State Highway Department undermined the
Reclamation
lined two sections of A Canal with a two inch layer of Gunite in 1927. On the
first schedule, they lined 400 feet of the left bank and 600 feet of the right
bank. The lining stretched 1,600 feet on the second schedule. Reclamation
deepened the
CCC
recruits on the project concentrated on maintenance and rodent control. Shortly
after moving into the Klamath region, CCC enlistees excavated a small drain in A
Canal to facilitate the removal of sediment. In 1936, they paved the canal with
concrete and rocks. Reclamation worked on enlargement of J Canal from February 3
to
Reclamation
added three foot high flashboard supports to Clear Lake Dam's spillway in 1938,
increasing the reservoir's capacity by about 60,000 acre-feet. The CCC raised
On
The
outbreak of World War II brought many changes to the Klamath Project.
Reclamation placed armed guards at major project facilities. Army engineers
began inspecting possible sites for a relocation camp on the Klamath Project
March 28, 1942. They located a site at Tule Lake, near Newell, California, and
the War Relocation Authority (WRA) started construction on April 18 of the same
year. Construction of sufficient housing for 10,000 Japanese finished on May 31,
1942, and the WRA started increasing camp facilities to house 6,000 more.
The
Interior Department signed an agreement with WRA Director Dillon Myer on June
22, 1942, giving the WRA 800 acres of Klamath Project land for the relocation
camp and another 35,000 acres for agricultural production. An agreement the
following December 14, added 683 acres to the camp site and 1,845 acres for
agriculture. Construction of the Tule Lake Relocation Camp affected work on the
Klamath Project, because it drew off all available labor and once again raised
wages.
The
WRA announced on July 23, 1943, it would segregate and house all
"disloyal" Japanese evacuees at the Tule Lake camp. On November 5,
1943, disturbances at the Tule Lake camp occurred. In response, the Army took
over operation of the camp. The Navy announced the takeover of the Klamath Falls
airport on October 28, 1943. Reclamation employed about thirty German prisoners
of war on the project for removing moss and some maintenance work. In 1945,
Japanese-American evacuees lined .86 miles of the M canal running through Tule
Lake camp.
The
N-16 lateral in the Tule Lake Division received a pre-fabricated asphalt lining
in 1949. High winds during placement operations, damaged the lining in a narrow
section of the lateral. Reclamation suspected the section was the source of
excessive seepage during testing, so the engineers segregated the section.
However, in tests, the wide section lost more water, through seepage, than the
narrow section. Engineers determined lower water levels reduced the amount of
seepage.
Gerber
Dam began showing seepage in its horizontal and vertical construction joints in
early 1951, apparently caused by improper cleanup of the joints during
construction. Engineers recommended a liquid neoprene (synthetic rubber) lining
to seal the joints. Reclamation scheduled repairs to start on October 1, 1951,
when Gerber Reservoir reached its lowest point, with 25.4 feet of the dam
exposed. Crews chipped out the disintegrated concrete, wider on the inside than
outside, and put new concrete in. They brushed the neoprene over the seams,
extending it six inches on either side of the joints.
Secretary
of the Interior Stewart L. Udall approved a contract with Pacific Power and
Light Company (California-Oregon Power) for development of the Keno Canal in
June 1967. In May 1970, the Tulelake Irrigation District held a public
dedication changing the name of the Lower Lost River Diversion Dam. They renamed
it the Anderson-Rose Dam in honor of the founders of the irrigation district;
Sam Anderson and Ivan Rose.
Settlement of the Project
The
Klamath Water Users' Association (KWUA) ratified the contract with the
Department of the Interior on November 3, 1905. Original estimates placed the
cost of the project to water users at $20 a month. In 1908, Reclamation
announced it would charge the water users $30 per month, but the water users
denied liability for the extra $10. On January 25, 1909, Secretary of the
Interior Richard A. Ballinger ordered construction on the Klamath Project
suspended. The KWUA gave in, agreeing to pay the additional charge, and
construction resumed.
The
Klamath Project attracted people of varying national origins to work on farms or
the project. The Project History of 1913, recorded three families each of
Russians and Swiss moved onto project lands. Many farmers found themselves hard
pressed to make payments on their bills. A group of Russian families, living
near Lost River Dam, left after selling in 1916; not able to keep pace with
their expenses. Despite such financial difficulties J. B. Bond; the Project
Manager in 1917, remained optimistic. He wrote, "The procedure of
foreclosing mortgaged property under the project is becoming unknown, and it is
a safe prediction that it will soon be spoken of as `a lost art'."
Potential
farmers also remained optimistic. In a public drawing during the spring of 1917,
175 filed for 42 tracts of land. Surrounding communities, especially Klamath
Falls, Oregon, grew along with the rural population (see Table I.). Merrill,
Malin, and Midland, the other project towns grew less rapidly, and in some cases
decreased. Construction of Malone Dam allowed the irrigation of 6,040 acres of
the Langell Valley Division's west side, and 4,532 near Bonanza, Oregon, making
that town of 300 part of the project. The Horsefly and Langell Valley Irrigation
Districts formed by 1925, and the Sunnyside Irrigation District in 1926. The
Malin and Shasta View Pumping Districts formed about the same time, and 8,000
acres of their land received water from the enlargement of the Adams Canal.
Klamath Falls reached a population of 10,000 people in 1926.
Reclamation opened land entries in the Klamath Project, to World War I veterans, between November 1922 and January 27, 1923. Afterward, Reclamation opened the entries to any applicants. Secretary of the Interior Hubert Work issued Public Order no. 19 in 1927, opening 145 farm units in the Tule Lake Division. Klamath Falls had a population of 15,000 by the end of the decade. The project's farm population grew to 2,833 by 1934.
Table I.
Klamath Project Populations, 1918, 1922, and 1946.
|
City |
Year |
Population |
|
|
Klamath
Falls |
1918 |
5,000 |
|
|
|
1922 |
7,000 |
|
|
|
1946 |
30,951 |
|
|
Bonanza |
1946 |
262 |
|
|
Malin |
1918 |
100 |
|
|
|
1922 |
200 |
|
|
|
1946 |
570 |
|
|
Merrill |
1918 |
600 |
|
|
|
1922 |
500 |
|
|
|
1946 |
-- |
|
|
Tulelake |
1946 |
915 |
|
|
Project
Farms |
1918 |
1,480 |
|
|
|
1922 |
1,300 |
|
|
|
1946 |
860 |
Source: Reclamation, Project History, Klamath Project, 1918, 141;
Reclamation, Project History, Klamath Project, 1922, 199; Reclamation, Project
History, Klamath Project, 1946, 140
Klamath
Falls boomed with the advent of World War II, reaching 25,968 people in 1945,
but the farm population dropped 2,812 people from 1934. Klamath Falls started
declining by 1950, though the other project towns continued to increase. The
farm population reached 4,255 in 1951. The Klamath Project's population declined
more heavily in the late twentieth century. The farm population fell to 1,825 by
1979. Klamath Falls retained only 17,737 of its boom population by 1990.
Merrill, Malin, Bonanza, and Tulelake had a combined population of 2,862 in the
1990 census. Midland did not even appear.
Reclamation
regained control of relocation center lands in 1946, including Tulelake. During
the same year the Bureau opened land entries to veterans returning from World
War II. Surplus farm equipment and abandoned barracks buildings greatly aided in
the veterans' settlement. Reclamation separated the barracks into smaller
structures, and the buildings provided temporary housing for the new settlers.
The veteran settlers on Klamath included Eleanor Jane Bolesta, a former WAVE who
became the first woman homesteader on a Reclamation project. Bolesta's husband,
Charles, a Marine during the war; received debilitating wounds while fighting on
Guam.
Uses of Project Water
The
Klamath Project primarily supplied irrigation water for local agriculture. The
project irrigates over 200,000 acres on about 1,400 farms. Farms on the project
grow a wide variety of crops (see Table II.). Forage crops for livestock
comprised the majority grown in the early years of the project. Early reports
showed alfalfa lands valued at twenty to thirty dollars an acre at the time of
Klamath's authorization. By 1910, the value increased to $50 an acre, rising to
$100 by 1912.
Potatoes
moved up in value on the Main Division during the 1920s. Acreage devoted to
potatoes increased by almost 600 from 1925-26. The monetary return increased
from $127,254 to $266,850 during the same year. At the same time alfalfa yields
on the Tule Lake Division increased by 20 percent. The project further supports
a large livestock business. Cattle, sheep, and hogs comprise most of the
project's livestock.
The
Klamath Project provides many activities for people interested in water sports
and outdoor recreation. The area is ripe for swimming, boating, water skiing,
camping, and hunting. The Fish and Wildlife Service operates recreational
facilities at Lower and Upper Klamath, and Tule Lakes. The Fish and Wildlife
Service manages the Clear Lake National Wildlife Refuge which includes Clear
Lake Reservoir. The Bureau of Land Management administrates the facilities at
Gerber Reservoir. Reclamation operates facilities at Malone Dam.
Table
II. Crops
grown on the Klamath Project, 1979. * indicates crops listed in 1960, but not
1979.
|
Cereals |
Forage |
Field |
|
|
Barley |
Alfalfa
Hay |
Beans |
|
|
Corn |
Pasture |
Cotton |
|
|
Oats |
Hay |
Hops |
|
|
Rice |
Silage |
Peppermint |
|
|
Rye |
Ensilage |
Spearmint |
|
|
Sorghums |
Alsike
Clover* |
Sugar
Beets |
|
|
Wheat |
|
Soybeans |
|
|
Fruits |
Nuts |
Vegetables |
|
|
Apples
|
Almonds |
Asparagus |
|
|
Apricots |
Pecans |
Beans |
|
|
Berries |
Walnuts |
Broccoli |
|
|
Cherries |
|
Cabbage |
|
|
Dates |
|
Carrots |
|
|
Grapefruit |
|
Cauliflower |
|
|
Grapes |
|
Celery |
|
|
Lemons |
|
Cucumbers |
|
|
Limes |
|
Greens |
|
|
Olives |
|
Lettuce |
|
|
Oranges |
|
Melons |
|
|
Peaches |
|
Onions |
|
|
Pears |
|
Peas |
|
|
Plums |
|
Peppers |
|
|
Prunes |
|
Potatoes |
|
|
Tangerines |
|
Squash |
|
|
|
|
Sweet
Corn |
|
|
|
|
Tomatoes |
Source:
Reclamation, Project History, Klamath Project, 1960, 22; Reclamation, Project
History, Klamath Project, 1979, w-2-w-4
Reclamation
established experimental farms in the marsh lands near Lower Klamath Lake in
1912. They drained water from the marsh and attempted to reclaim the land. The
tule in the marsh became difficult to till after it dried, limiting Reclamation
to one acre of land on the farm. Reclamation tried to grow a variety of crops on
the farms, but many died. Grains and grasses survived, but did not reach normal
growth. The Army Board of Engineers, of 1910, reported the experimental farms
were not self-supporting, and operated at the expense of project farmers. The
Army recommended the Department of Agriculture assume control. Reclamation
turned the farms over to the Klamath County Agriculturalist in 1914.
Conclusion
Events on the
Klamath Project mirrored events in the western United States. The project
witnessed labor fluctuations and home front activities during war. The agreement
between Reclamation and California-Oregon Power, leading to construction of the
Link River Dam, created an unusual circumstance in Reclamation projects. A power
company building and operating a dam on a project, did not often occur. Most
important the Klamath Project participated in the ongoing quest for water,
indigenous to the American west, and answered the increasing demand for
irrigation. Facilities on the Klamath Project continue to provide a large
population with a variety of services.
About the Author
Eric
A. Stene was born in Denver, Colorado, July 17, 1965. He received his Bachelor
of Science in History from Weber State College in Ogden, Utah, in 1988. Stene
received his Master of Arts in History from Utah State University in Logan, in
1994, with an emphasis in Western U.S. History. Stene's thesis is entitled The
African American Community of Ogden, Utah: 1910-1950.
Bibliography
Manuscripts and Archival Collections
Record Group 115. Department of the Interior. Bureau of Reclamation Records. National Archives and Records Administration, Denver office.
Annual Project History, Klamath Project: 1912-15, 1917-30, 1934-43, 1945-46, 1950-51, 1959-60, 1979.
Operation and Maintenance Report, Klamath Project, 1916.
Project Reports.
"Report on the Seepage Test of the Experimental Buried Prefabricated Asphalt Membrane Lining Test Section in the N-16 Lateral of the Klamath Project." Compiled by Brooks O. Custer. Edited by Mark D. Taylor, Jr., January 1951. Box 473.
"Report on Repair of Gerber Dam with Neoprene Membrane." Box 473.
Government Documents
Department of Commerce. Bureau of the Census. Twenty-First Census of the United States, 1990: Population and Housing. Bureau of the Census, 1990, on CD-ROM.
Water and Power Resources Service. Project Data. Denver: Government Printing Office, 1981.
Books
Conrat, Marie and Richard. Executive Order 9066: The Internment of 110,000 Japanese Americans. California Historical Society: Sacramento/Los Angeles, 1972.
Gray, Edward. An Illustrated History of Early Northern Klamath County, Oregon. Bend, Oregon: Maverick, 1989.
Palmberg, Walter J. Copper Paladin: A Modoc Tragedy; A Story of the Two Principal Role-Players of the Modoc Indian War of 1872-73. Bryn Mawr, Pennsylvania: Dorrance & Co., 1982.
Stone, Buena Cobb. Fort Klamath: Frontier Post in Oregon; 1863-1890. Dallas: Royal Publishing, 1964.
Articles
Darr, A. L.. "Gerber Dam Construction, Klamath Project, Oregon." New Reclamation Era. December 1925, 182-84.
"Malone Diversion Dam Built." The Reclamation Record. August 1923, 285-86.
"Oregon-California Farms Open to Entry." The Reclamation Record. November 1922, 285.
Thomas, E. H.. " Livestock at the Klamath County Fair." The Reclamation Record. December 1921, 548-49.
Thye, Carl J. " The Bureau Reclaims Its Own." The Reclamation Era. April 1947, 90-92.
"Tule Lake Lands Opened to Veterans." The Reclamation Era. September 1946, 202.
"War Relocation Centers Acquired." The Reclamation Era. September 1946, 195.
Other
Parker, Sybil B., ed. McGraw-Hill Dictionary of Scientific and Technical Terms, 4th Edition. New York: McGraw-Hill, 1989